Infosys – eBook | 31
6.3.1 Move Build Package Template (Illustrative) 
Particular 
Description 
Bundle ID 
<Unique Bundle / Move Group Identifier> 
Application ID 
<Unique Application / Infrastructure Identifier> 
Application Name 
<Brief description about the application / infrastructure> 
Line of Business 
<Business unit name> 
Target AO 
<Bronze / Silver / Gold/ Platinum> 
Target RTO 
<hh:mm> 
Target RPO 
<1-5> 
Component Type 
<Application / Infrastructure / Other Software> 
Application environment 
<Mainframe / Distributed / Both> 
Application Manager 
<Name> 
Technology Delivery Manager 
<Name> 
System Administrator 
<Name>
Build Pr
participating application an application build package is created based on Current & Target state Application & Infrastructure 
analysis / design work conducted earlier.
6.3.2 Application Build Package template (Illustrative)
Particular
Description
Application ID
<Unique Application / Infrastructure Identifier>
Target Server /s 
(Relocate from Source 
Data Center)
Source Data Center’s Server Information
Server 
Hostname
Server Type 
(Web/App/DB)
Vendor
Model
OS
Security Zone
CPU type, size 
& count
Memory
Local Disk size
Location
Software
Target Server /s 
(Physical Builds)
Source Data Center’s Server Information
Server 
Hostname
Server Type 
(Web/App/DB)
Vendor
Model
OS
Security Zone
CPU type, size 
& count
Memory
Local Disk size
Location
Software
Target Server /s 
(Virtual Builds)
Source Data Center’s Server Information
Server 
Hostname
Server Type (Web/App/DB)
Virtual Memory 
Security Zone
Virtual 
processor 
count 
OS 
Local Disk size
Location
Software
Appliances Needed
Appliances Needed
Third Party Circuit 
Details
<Circuit info> e.g. New York to Atlanta 1 Gbps AT&T <circuit id>
Convert pdf slides to powerpoint online - C# Create PDF from PowerPoint Library to convert pptx, ppt to PDF in C#.net, ASP.NET MVC, WinForms, WPF
Online C# Tutorial for Creating PDF from Microsoft PowerPoint Presentation
convert pdf to editable ppt online; pdf to ppt
Convert pdf slides to powerpoint online - VB.NET Create PDF from PowerPoint Library to convert pptx, ppt to PDF in vb.net, ASP.NET MVC, WinForms, WPF
VB.NET Tutorial for Export PDF file from Microsoft Office PowerPoint
embed pdf into powerpoint; picture from pdf to powerpoint
32 | Infosys – eBook
Particular
Description
Databases 
Database Information 
Database Name 
Database Type (Oracle/
DB2/Sybase etc.)
Instance Name 
Database Server 
Hostname 
Storage 
Storage Information 
Hostname 
Storage Tier 
Allocated SAN /NAS Storage Size 
Network & Security 
Network & Security Information 
Hostname
IP address
Firewall Rules (if any) Static Routes (if any) 
6.4 Update Disaster Recovery Plans 
After having completed the detailed analysis of an application’s target state, it is important to update all the Disaster Recovery 
documents prior to their migration. The Disaster Recovery Plan comprises of both, the Application and Infrastructure 
Recovery Plans. Necessity to update Disaster Recovery plans may be required because of one or more target state scenarios 
mentioned (but not limited to) below: 
• Changes to Application Architecture to meet target service level objectives defined by business. 
• Physical to Virtual Server Deployment 
• Technology Refresh to overcome retiring Hardware and OS issues 
• Changes to physical deployment architecture to overcome any network latency / performance issues 
• Revisions in High Availability / Data Protection implementation 
• Changes in other Applications / Infrastructure / Shared Services environment impacting the type of integration with an 
application. 
Business continuity team is generally engaged in making changes to current Disaster Recovery Plans (DRP) to ensure that 
Recovery plans are updated considering all facets viz. Workflows, Technologies & Processes. 
6.5 Create Detailed Implementation plan 
Now that we have a full clarity on Target Applications, Infrastructure and move considerations, a detailed implementation 
plan needs to be created. This plan should detail following activities (illustrative) 
• Scope, Phases & Statement of Work for various work streams of the program 
• Detailed cost breakup & funding approvals 
• Procurement of necessary hardware & software 
• Network 
• Servers 
• Application & Infrastructure Software 
• Storage 
• Security 
• Integrated Program Schedule in view of Infrastructure readiness at Target Data Center, 
• Availability of change windows, key resources, equipment etc. 
• Roles & Responsibilities for Build & Test activities 
• Team structure 
• Education & training 
• Relocation / Deputation of resources 
VB.NET PowerPoint: Read, Edit and Process PPTX File
split PowerPoint file, change the order of PPTX sildes and extract one or more slides from PowerPoint How to convert PowerPoint to PDF, render PowerPoint to
how to convert pdf slides to powerpoint presentation; convert pdf pages into powerpoint slides
C# PowerPoint - How to Process PowerPoint
slide processing library provides users with access to operate PowerPoint slides/pages in the simplest procedures, for instance, using online clear C# methods
how to change pdf to powerpoint; change pdf to powerpoint on
Infosys – eBook | 33
• Project Management Plans 
• Scope Management Plan 
• Change Management Plan 
• Risk Assessment & Mitigation Plan 
• Risk Management Plan 
• Communication Plan 
• Schedule Management Plan 
• Cost Management Plan 
• Progress Tracking Tools / Repositories 
• Documented procedures & processes to Build & Test 
• Pre-Move / Post Move validation Checklists 
• Core Infrastructure installation & configuration plan 
• Third Party Network circuits 
• Co-ordination with External vendor Services 
• Forklift / Trucking (As needed) 
• Application Service Providers - ASPs (As needed) 
• Network Carriers (As needed) 
• Sub-contractors (As needed) 
• Identification of stakeholders for sign-offs on Build & Test milestones. 
Risk Area Typical Risk / Challenge 
Mitigation Option 
Planning 
& Design 
Phase 
• Complexity of interdependencies between various 
applications and sharing of hardware poses 
availability risk while migrating applications 
• Detailed application interdependencies analysis 
and individual mitigations to either unlink 
dependency transfer the dependency to another 
application / hardware. 
• Some legacy applications run on obsolete / 
unsupported Hardware & OS. While migrating 
to new data center, the intent is to migrate to 
newer Hardware, OS but Legacy Application is not 
supported on the newer Hardware/OS 
• Some vendor supported software & tools are 
not compatible with technology refresh activities 
included in the Migration 
• Re-architect the application to be able to host on 
newer Hardware / OS platform
• Virtualize older OS versions (wherever possible) 
until application is re-architected. This may also 
be a better option if application is anticipated to be 
sunset in the short term. 
• Increased distance between new data centers 
disables from utilizing Active - Active / load 
balancing deployment pattern
• Transfer Availability dependency to local / other 
nearby data centers i.e. enhancing the redundancy 
& capacity.
• Implement Network & Storage configuration 
changes
• Budgetary constraints consistently driving changes 
to program scope 
• Divide the program scope into multiple phases 
based on priorities to prevent from losing focus on 
at least critical phases because of such constraints.
VB.NET PowerPoint: Process & Manipulate PPT (.pptx) Slide(s)
add image to slide, extract slides and merge library SDK, this VB.NET PowerPoint processing control powerful & profession imaging controls, PDF document, image
converter pdf to powerpoint; images from pdf to powerpoint
VB.NET PowerPoint: Sort and Reorder PowerPoint Slides by Using VB.
clip art or screenshot to PowerPoint document slide large amount of robust PPT slides/pages editing powerful & profession imaging controls, PDF document, image
how to change pdf to powerpoint on; convert pdf slides to powerpoint online
34 | Infosys – eBook
6.6 Regulatory Considerations 
There are various Regulatory requir
data. Generally, depending upon the location of the data center, relevant country specific regulations are applicable. Below are 
some of the regulatory considerations that should be complied to while engineering / re-engineering data centers. 
Telecommunication Infrastructure Standards (TIA-942) 
TIA-942 is a standard developed by the Telecommunications Industry Association (TIA) to define guidelines for planning and 
building data centers, particularly with regard to cabling systems and network design. The standard deals with both copper 
and fiber optic media. 
The TIA-942 specification references private and public domain data center requirements for applications and procedures 
such as: 
• Network architecture 
• Electrical design 
• File storage, backup and archiving 
• System redundancy 
• Network access control and security 
• Database management 
• Web hosting 
• Application hosting 
• Content distribution 
• Environmental control 
• Protection against physical hazards (fire, flood, windstorm) 
• Power management 
Grounding Standards (TIA-607) 
The purpose of this Standarounding systems 
telecommunications grounding and bonding infrastructure supports a multi-vendor, multi-product environment as well as 
the gremises. 
OSHA Electrical Safety requirements 
Its mission is to prevent work-related injuries, illnesses, and deaths by issuing and enforcing rules (called standards) for 
workplace safety and health. OSHA’s electrical standards are designed to protect employees exposed to dangers such as 
electric shock, electrocution, fires, and explosions. 
National Electrical Code (NEC) 
The National Electrical Code (NEC) is a United States standard for the safe installation of electrical wiring and equipment. It 
is part of the National Fire Codes series published by the National Fire Protection Association (NFPA). 
NEPA - National Environmental Policy Act 
NEPA requires agencies to undertake an assessment of the environmental effects of their proposed actions prior to making 
decisions. It offers analysis of the environmental effects of the proposed action and possible mitigation of potential harmful 
effects of such actions. 
HIPAA - Health Care Companies data processing 
HIPAA regulation includes the establishment of national standards for electronic health care transactions and national 
identifiers for pr
security and data privacy requirements for organizations handling healthcare information. 
VB.NET PowerPoint: Use PowerPoint SDK to Create, Load and Save PPT
Besides, users also can get the precise PowerPoint slides count as soon as the PowerPoint document has been loaded by using the page number getting method.
how to convert pdf to ppt; pdf to powerpoint converter
VB.NET PowerPoint: Extract & Collect PPT Slide(s) Using VB Sample
want to combine these extracted slides into a please read this VB.NET PowerPoint slide processing powerful & profession imaging controls, PDF document, image
how to convert pdf to powerpoint; online pdf converter to powerpoint
Infosys – eBook | 35
Sarbanes Oxley - Data Protection and Retention 
otect shareholders and the general public 
from accounting errors and fraudulent practices in the enterprise. The act is administered by the Securities and Exchange 
equirements. 
e records; rather, it defines 
which records are to be stored and for how long. The legislation not only affects the financial side of corporations, it also 
affects the IT departments whose job it is to store a corporation’s electronic records. The Sarbanes-Oxley Act states that all 
business records, including electronic records and electronic messages, must be saved for “not less than five years.” 
6.7 Enterprise Contractual considerations 
Today’s Data Center environments are a blend of in-house & vendor supported infrastructure. Overlooking these contractual 
obligations may have huge cost and/or legal implications. Below are some of the contractual considerations that should kept 
in mind while conducting a data center migration. 
• Lease agreements with Hardware V
require necessary permissions / negotiations with leasing vendor prior to relocation to target data center. 
• Any existing maintenance contracts with IT hardware vendors should be evaluated prior to planning a voluntary 
retirement / decommissioning. 
• Network Communication links are also generally provided on fixed duration like 6 month / 1 year contract type. So, 
• Current Data Center facilities lease agreements (if any) will also need to be seen. E.g. notice period required to vacate 
current data center space & any maintenance contracts for Power, UPS, HVAC, Fire Suppressions systems and other 
facilities should be evaluated prior to scheduling migration. 
Build Applications & Infrastructure - Target Data Center 
7.1 Core Infrastructure & Shared Services Build & Readiness Testing 
Now that we have a detailed implementation plan, before we can migrate applications & their servers, core infrastructure & 
Enterprise Shared Services need to be in place at target data center. Core infrastructure serves as common backbone for all the 
applications & any unavailability of the same in the production environment will adversely impact a significant number of 
applications. Therefore, every core infrastructure component should be built with appropriate level of redundancy & should 
have enough capacity. 
Below are some of the illustrative Core Infrastructure & Shared services Build Activities that should be undertaken at target 
data center 
• Racks, Physical mounting of hardware 
• Installation & Configuration of Core Infrastructure components: 
• Network Switching & Routing environment 
• SAN / NAS / Backup Infrastructure 
• Firewalls, IDS & other security appliances 
• Activation of Network Connections with carriers. 
• Creation of Security Zones 
• Installation & Configuration of Enterprise Shared Services 
• Authentication & Authorization (Identity Management etc.) 
• Logging & Monitoring (Servers, Databases, OS etc.) 
• Antivirus & Anti-spyware 
• Shared Databases (Oracle RAC etc.) 
• Messaging (Email, MQ etc.) 
• File Sharing (FTP, NDM etc.) 
• Security Services (Digital Certificates / PKI etc.) 
VB.NET PowerPoint: Merge and Split PowerPoint Document(s) with PPT
of the split PPT document will contain slides/pages 1-4 code in VB.NET to finish PowerPoint document splitting If you want to see more PDF processing functions
how to convert pdf to powerpoint in; pdf into powerpoint
VB.NET PowerPoint: Complete PowerPoint Document Conversion in VB.
It contains PowerPoint documentation features and all PPT slides. Control to render and convert target PowerPoint or document formats, such as PDF, BMP, TIFF
image from pdf to ppt; how to convert pdf to powerpoint in
36 | Infosys – eBook
• Testing of Core Infrastructure & Shared Services: 
• Intranet, Extranet, Internet & VPN connectivity testing 
• High Availability / Failover testing 
• Performance / Stress testing 
• Ethical Hacking / Vulnerability Assessment / Penetration testing 
• Shared Services Availability & Integrity testing 
7.2 Pilot Applications – Build & Test 
At this point, it is recommended to gr
envir
• Implementation plan is flawless 
• All internal & external dependencies have been taken care of. 
• To confirm the feasibility of build on a specific technology & environment 
• Actual Migration time is within available change window 
• No business services are being hampered in an unplanned fashion. 
• Hardware & Software for application (as per target design) are compatible. 
Below is a list of illustrative application’
• Installation & Testing of 
• Application Specific Servers (Web / App / DB etc.) 
• Application specific software & necessary patches (.NET, Java, Oracle Apps etc.) 
• Core Business Application / Service (Core Banking / ecommerce / Payroll etc.) 
• Necessary client software (FTP / NDM / MQ / Backup clients etc.) 
• Provisioning & Testing of 
• Application specific Network Access & Security e.g. (Firewall Rules / Static Routes) 
• 
• Interconnectivity with other applications & enterprise shared services 
• Data Migration & Acceptance testing (for New Server builds only) 
• Load snapshot of data from Source Data Center 
• Conduct test transactions on the application 
• Capture test results and incorporate any lessons learned in the build & test plans of Move Bundle Groups. 
Lessons learned from the pilot implementation may suggest some alternatives / mitigation steps to enhance the 
implementation plan for successful build & test activities. 
7.3 Build Move Bundle Packages 
Based on the lessons learned from pilot implementation activities discussed above, we are set to execute the move bundle 
& application build packages defined earlier. Successful execution of move bundle packages requires excellent program 
VB.NET PowerPoint: Convert & Render PPT into PDF Document
Using this VB.NET PowerPoint to PDF converting demo code below, you can easily convert all slides of source PowerPoint document into a multi-page PDF file.
adding pdf to powerpoint; change pdf to powerpoint online
VB.NET PowerPoint: Add Image to PowerPoint Document Slide/Page
insert or delete any certain PowerPoint slide without methods to reorder current PPT slides in both powerful & profession imaging controls, PDF document, tiff
online pdf converter to powerpoint; change pdf to ppt
Infosys – eBook | 37
Based on the move bundle group’s composition, generally a move bundle group requires co-ordination between various 
resources on a full time / part-time basis. Below are some of the illustrative roles for a typical move group: 
• Build Project Manager 
• Build Specialist (s) e.g. Unix / Intel specialist 
• SMEs of Applications included in Move Bundle. (e.g. Application Architect, Application Manager, Technology Delivery 
Manager
• System Administrator for servers included in the relevant application build packages. 
• Data Center Operations team – for allocation of Space / Rack / cabling / Power & other facilities. 
• Server Virtualization team – for virtual server builds, as applicable. 
• Data Center Infrastructure Engineering team – Storage, Network, and Security etc
Each organization follows its standard operating procedures for provisioning of servers. These should be followed in build 
activities. Further, as discussed earlier migration of a server to a target data center can fall under one of the following 
categories: 
• Building a New Physical Server 
• Building a new Virtual Server 
• Moving / Fork-lifting existing server 
Building new physical / virtual servers does not interrupt existing operations at source data center whereas Moving / Fork-
lifting existing servers from source data center require additional planning and co-ordination for a seamless relocation. 
Appropriate change windows need be co-coordinated with application, business & support teams. Further, standard 
shutdown and startup procedures & checklists will need to be followed to ensure that all services are successfully restored in 
the target data center. 
7.4 Test Move Bundle Packages 
A series of test cycles is necessary to ensure that all build activities meet the program goals. Generally, following test events 
are adequate 
7.4.1 Unit Testing 
Once each application build package gets implemented, it’s important to conduct a unit testing for all components of that 
application. This test ensures that Hardware, Operating System, Application Modules and associated software components 
are functional as expected. All interconnectivity within different Tiers of an application e.g. Web to App / App to DB are 
tested in this test cycle. Further, stress testing for various servers of an application is also carried out at this stage to ensure 
that hardware is capable of meeting desired performance levels for a given workload. 
7.4.2 Shared Infrastructure Testing 
chitecture, there is a need to test all interfaces to 
Shared Services environment. e.g. if an application requires a Shared Database / a Digital Certificate / Authentication Service 
then necessary tests should be conducted to ensure that relevant users / queries / RPCs etc. are performing successfully. A 
stress testing on Shared infrastructure potion is also expected in this test cycle. This will provide feedback for capacity and 
scalability of Shared Infrastructure environment. 
7.4.3 System Integration Testing – Move Group level 
Next level of testing is to ensure that all interdependent applications within a move group / under the purview of a build 
project manager are able to successfully interact with each other. e.g. if an application A in Move Bundle Group 1 needs to 
oup, then some sample files may need to be 
transmitted between the two applications to ensure the network connectivity, performance, configuration parameters. 
38 | Infosys – eBook
7.4.4 System Integration Testing – Program level 
This final test is generally managed by a program level test manager. The purpose of this test is to ensure that all inter Move 
group dependencies ar
those that were not in the same Move Bundle group as that of the application. 
7.5 Typical Risks, Challenges & Mitigation options – Build & Test Phase 
Risk Area Typical Risk / Challenge 
Mitigation Option 
Build 
& Test 
Phase 
• Interdependencies on multiple work streams 
& their timely readiness such as Data Center 
Facilities, Equipment availability, Core & Shared 
Service Infrastructure, Third party Vendor circuits 
pose risk to Build & Test schedule 
• Set up a PMO to manage multiple work stream 
projects
• Adopt PMI best practices for project management 
• Define Bill of Material & initiate Procurement 
processes earlier in the cycle to accommodate 
sufficient lead time.
• Procurement & equipment delivery times are high 
and have tendency to impact Build Schedule 
• Enterprise resources are engaged in day to day 
operational activities depriving the necessary focus 
on build and test migration activities 
• Engage professional services partner for a smooth 
migration.
• Inability to test all the interdependent applications 
in a single test cycle as some interfacing 
applications is not ready yet. 
• Sequence the build activities appropriately to finish 
the build of closely related applications around the 
same time. 
• Ensure that dependent Enterprise Shared Services 
are ready by completion schedule of dependent 
applications
• Ensure that firewalls rules & other connectivity 
requirements are implemented & tested prior to 
application level test activities. 
• Security zones & network connectivity is not 
ready
• Ensure that third party circuits are commissioned 
in time & Vendors are ready to support the tests as 
applicable.
Roll out & decommission 
Now that we have built and tested all relevant applications & infrastructure at target data center, it is the time to commence 
the rollout activities. 
• Application Criticality (Based on its Service level objectives) 
• Number & Type of Servers 
• Interdependencies with Shared Infrastructure & other business applications. 
• Type of Build (Relocated / Built a new physical server / Virtualized) 
• Associated Databases 
• External Storage (On SAN / NAS / Tape media) 
• Third Party Network & Software dependencies 
• Change Windows & Availability of key contacts. 
• Data Migration plan (from Source to Target Data Center) 
• Additional Resource requirements 
Infosys – eBook | 39
Decommissioning is the last part of the program after successful rollout. The objective of decommissioning is basically to 
• Release and clean up Infrastructure at source data center. 
• Data Archives 
• Power-off / Enable re-use of released hardware 
• Update Asset Management systems to reflect release of hardware and software from Source Data Center. 
• Free up racks, power and data center space for other IT initiatives. 
We will discuss on these two in further detail in the next section: 
8.1 Rollout / Cutover applications to Target Data Center 
Data Migration is a biggest challenge for a successful cutover / rollout of an application. This is primarily applicable to the 
new physical / virtual server builds. It is expected that application whose all servers have been relocated from source to target 
data center have already been connected to target storage environment and their data migration has already been taken care 
during build activity itself. 
Whereas, applications for which some servers have been built new whereas a few fall in forklift / trucking category, data 
migration needs to be planned appropriately. Below are some of the illustrative options in such scenarios: 
• Withhold Forklift/Trucking of any data sensitive servers until cutover change window to ensure that snapshot of data 
for all serdware relocation go hand in 
hand in this scenario. 
• If servers of an application are not latency sensitive / distance between target and source data centers does not add 
any latency, Forklift/ Truck relevant servers to target data center during build activity itself and continue running an 
application with infrastructure / servers split across two data centers until the time when data migration for all new 
om target data 
center’s infrastructure. This option may require additional assessment on capacity of network to handle data traffic 
between the two data centers, availability of data replication / storage infrastructure over the network. 
In the case of a physical / virtual server build since a new instance of application has been created at target data center at 
the same time when earlier instance is also functional at source data center, it is necessary to smoothly bring the operational 
data from source to target data center. This would additionally need that users are seamlessly being pointed to the target data 
center environment which would need necessary network and security configuration changes in the environment. 
Based on an application provide enough time 
to 
• Backup data from source data center environment 
• To discontinue new transactions until data is restored at the target data center 
• To redirect the users to utilize the target data center environment. 
Howevereal-time because of the 
• Ensuring the availability of application during transition 
• Integrity requirements of the data snapshot 
• Recording the incremental changes to data after snapshot taken 
• Restoration of incremental data during transition 
These requirements pose potential risks to data corruption & integrity. A careful planning is needed to ensure that data 
restoration is successful & achievable within the available change window. In many instances decisions such as airlifting a 
business critical data on a Chartered flight are needed to ensure the business continuity and security of business critical data. 
For some non-critical applications, replication of data over WAN or shipment through Tape backups may be an option. 
As an illustration, applications such as ecommerce, online banking, online brokerage etc. are critical business applications 
that are operational 24x7 and their data migration may be done through airlift to minimize the migration time, safeguard data 
security & reduce the probable impact to the business. Weekends are generally utilized for such events to minimize service 
outages. Other applications such as product catalogs / survey repositories / market trends etc. are comparatively less critical 
and alternate migration plan may work well for them. 
40 | Infosys – eBook
So the typical cutover activities include (but not limited to) are: 
Planning 
• Selection of a change window. 
• Identification of Change management team 
• Definition of Roles, Responsibilities, Processes to be followed during change window. 
• ogress of cutover activities and 
issues in hand. 
• AN / over iSCSI/ 
SAN etc.) 
• Business and Technology Partners for Post implementation validation testing 
• Checklist of critical business services that define the success criteria for an application’s migration. 
• Tools & templates to capture the test results / incidents for IT service management aspects 
• Compliance to any regulatory requirements in handling the data security & privacy. 
Configuration Changes 
• Engagement of Network & Security folks in changes to network routing, DNS, firewall rules, and load balancers etc. 
• Configuration & Readiness of external storage environment at target data center to receive the data being brought into 
target data center environment 
Testing & Validation 
• Conduct pilots as necessary in a test bed to ensure that data migration plan works as expected prior to moving entire 
production data store of an application. 
• Pre-Cutover and Post-Cutover validation testing. 
• Plan for point in time for restore based on business defined RTO/ RPOs. 
• T
production launch. 
• Tdependencies / application architecture 
including external vendors 
8.2 Decommissioning Source Data Center Hardware 
Though, a successful cutover/rollout is key to the success of a data center migration program, appropriate steps to 
decommission the source data center are necessary to ensure the IT infrastructure maintenance costs are optimized and all 
security, environmental and regulatory requirements are met. Typical decommissioning activities include: 
• Ensure that none of the applications / service is needed on the source data center infrastructure after the cutover of 
applications. In instances where some servers are shared across multiple applications, it is necessary to ensure that all 
stakeholders utilizing services / applications on a hardware are communicated about the decommissioning plans and 
• Decommissioning of certain applications that share hardware will need to wait until all the applications sharing that 
hardware have been successfully rolled out to target data center or their dependency / sharing on the hardware has 
been mitigated otherwise (e.g. moving to a different hardware / changes to application architecture that eliminates the 
need of shared hardware etc). 
• Archival of data for regulatory and compliance requirements (as necessary).Backup all software components / 
configuration files / scripts that may be needed in future. 
• onic hardware, data and media in transit. 
• Power-off servers & other hardware infrastructure that is released post cutover of applications... Based on the 
reusability of released hardware (Model, OS etc.), it may be reused for the build of other applications. This would save 
power, needless cooling in the data center and provide some re-usable equipment. 