Setting up material resources    
225
11
TIP
In addition to or instead of cost rates, a resource can include a set fee that 
Project accrues to each task to which the resource is assigned‮ This is called a cost 
per use. Unlike cost rates, the cost per use does not vary with the task’s duration 
or amount of work the resource performs on the task‮ You specify the cost per use 
in the Cost/Use field in the Resource Sheet view or in the Per Use Cost field in the 
Resource Information dialog box‮
Click OK to close the Resource Information dialog box‮
In the Resource Sheet view, note that Jane Dow’s initial rate, $55 per hour, appears in 
her Std. Rate field. This field will display $55 per hour until the current date changes 
to 6/1/15 or later‮ It will then display her new standard rate of $63‮25 per hour‮
Setting up material resources
Material resources are consumables that you use up as the project proceeds‮ On a 
construction project, material resources might include nails, lumber, and concrete‮ You work 
with material resources in Project to track a fixed unit amount or a rate of consumption of 
the material resource and the associated costs‮ Unlike work resources, you cannot enter 
a maximum units value for a cost resource or material resource‮ Because neither type of 
resource performs work, the maximum units value doesn’t apply‮ Although Project is not 
a complete system for tracking inventory, it can help you stay better informed about how 
quickly you are consuming your material resources, and at what cost‮
The scenario: At Lucerne Publishing, galley proofs of the new children’s book are the 
consumable resource that interests you most. These are high-fidelity mock-ups of the new 
book that are created before the book is commercially printed‮ Because these galley proofs 
are relatively expensive to have produced, you’d like to account for their costs in the plan‮ 
To do so, you need to create a material resource‮
In this exercise, you enter information about a material resource‮
In the Resource Sheet, click the next empty cell in the Resource Name column‮
Type 
Bound galley proofs
In the Type field, click the down arrow, select Material, and press the Tab key‮
Merge pdf - Merge, append PDF files in C#.net, ASP.NET, MVC, Ajax, WinForms, WPF
Provide C# Demo Codes for Merging and Appending PDF Document
batch pdf merger; best pdf combiner
Merge pdf - VB.NET PDF File Merge Library: Merge, append PDF files in vb.net, ASP.NET, MVC, Ajax, WinForms, WPF
VB.NET Guide and Sample Codes to Merge PDF Documents in .NET Project
batch pdf merger online; c# pdf merge
226
Chapter 11 Fine-tuning resource and assignment details 
In the Material Label field, type 
copies
Copies is the unit of measurement you’ll use for this material resource‮ You will see 
this label again in the section “Assigning material resources to tasks” later in this 
chapter‮
In the Std. Rate field, type 
15 
and then press Enter‮
This is the per-unit cost of this material resource; put another way, each copy of a 
bound galley proof costs $15‮ Later in this chapter, you’ll specify the unit quantity 
of the material resource when you assign it to tasks‮ Project will then calculate the 
cost of the material resource assignment as the per-unit cost that you entered above 
times the number of units on the assignment‮
The Material Label field applies only to material resources.
+
CLEAN UP
Close the Advanced Resources file.
So far in this chapter, you’ve focused on resource details‮ For the remainder of the chapter, 
your focus shifts to fine-tuning assignment details.
Delaying the start of assignments
If more than one resource is assigned to a task, you might not want all the resources to 
start working on the task at the same time‮ You can delay the start of work for one or more 
resources assigned to a task‮
For example, assume that four resources have been assigned a task‮ Three of the resources 
initially work on the task, and the fourth later inspects the quality of the work‮ The inspector 
should start work on the task later than the other resources‮
Online Merge PDF files. Best free online merge PDF tool.
Online Merge PDF, Multiple PDF files into one. Download Free Trial. Merge PDF, Multiple PDF files. Drag and drop your PDF or several files in the box above.
how to combine pdf files; pdf combine pages
C# WPF PDF Viewer SDK to view, annotate, convert and print PDF in
C#, C# convert PDF to HTML, C# convert PDF to Word, C# extract text from PDF, C# convert PDF to Jpeg, C# compress PDF, C# print PDF, C# merge PDF files, C# view
acrobat merge pdf files; c# merge pdf pages
Delaying the start of assignments    
227
11
The scenario: At Lucerne Publishing, the new children’s book plan includes a task to which 
both a copyeditor and the book author, Tad Orman, are assigned‮ The intent of this task is 
that the author will review the edits made to his book manuscript, and shortly afterward, 
the copyeditor will begin to incorporate the author’s feedback‮ Right now, both resources 
are assigned work throughout the duration of the task, but you’d like to delay the start of 
the copyeditor’s work by two working days‮
In this exercise, you delay the start of a resource assignment on a task‮
SET UP
You need the Advanced Assignments_Start file located in your Chapter11 
practice file folder to complete this exercise. Open the Advanced Assignments_Start file, 
and save it as Advanced Assignments.
On the View tab, in the Task Views group, click Task Usage‮
As you might recall from Chapter 9, “Advanced task scheduling,” the Task Usage view 
groups the assigned resources below each task‮
In the Task Name column, below task 18, Author review of content edit, click the 
assigned resource Copyeditors
On the Task tab, in the Editing group, click Scroll to Task‮
As you can see, this task currently has two resources assigned to it: a copyeditor and 
the new book’s author, Tad Orman‮
Next you’ll delay the copyeditor’s assignment in the Task Usage view‮
On the Format tab, in the Assignment group, click Information‮
The Assignment Information dialog box appears‮ 
VB.NET Create PDF from PowerPoint Library to convert pptx, ppt to
C#, C# convert PDF to HTML, C# convert PDF to Word, C# extract text from PDF, C# convert PDF to Jpeg, C# compress PDF, C# print PDF, C# merge PDF files, C# view
break pdf file into multiple files; pdf mail merge plug in
VB.NET Create PDF from Word Library to convert docx, doc to PDF in
C#, C# convert PDF to HTML, C# convert PDF to Word, C# extract text from PDF, C# convert PDF to Jpeg, C# compress PDF, C# print PDF, C# merge PDF files, C# view
pdf combine; pdf mail merge
228
Chapter 11 Fine-tuning resource and assignment details 
Click the General tab if it is not already selected, and then in the Start box, type or 
select 
5/4/15
Click OK to close the Assignment Information dialog box‮
Project adjusts the copyeditor’s assignment on this task so that he works no hours on 
Thursday or Friday‮
The duration of this task has increased because 
the work is over a longer period of time.
Now, in the timephased portion of the view, you can see that zero hours of work are 
scheduled for the copyeditor on Thursday and Friday, April 30 and May 1‮ The other 
resource assigned to the task is not affected‮ Note that the total work of this task did 
not change, but its duration did—the finish date moved out two working days.
VB.NET PDF- HTML5 PDF Viewer for VB.NET Project
C#, C# convert PDF to HTML, C# convert PDF to Word, C# extract text from PDF, C# convert PDF to Jpeg, C# compress PDF, C# print PDF, C# merge PDF files, C# view
merge pdf online; build pdf from multiple files
C# HTML5 PDF Viewer SDK to view PDF document online in C#.NET
C#, C# convert PDF to HTML, C# convert PDF to Word, C# extract text from PDF, C# convert PDF to Jpeg, C# compress PDF, C# print PDF, C# merge PDF files, C# view
append pdf; batch combine pdf
Applying contours to assignments    
229
11
TIP
If you want an assignment to start at a specific time as well as on a specific date, you 
can specify the time in the Start box‮ For example, if you want the copyeditor’s assignment 
to start at 1 P‮M‮ on April 30, type 
4/30/15 1:00 PM
‮ Otherwise, Project uses the default 
start time‮ To change the default start time, on the File tab, click Options‮ In the Project 
Options dialog box, click the Schedule tab, and in the Default Start Time field, enter the 
value that you want‮
Applying contours to assignments
In the Resource Usage and Task Usage views, you can see exactly how each resource’s as-
signed work is distributed over time‮ In addition to viewing assignment details, you can 
change the amount of time a resource works on a task in any given time period‮ There are 
various ways to do this:
Apply a predefined work contour to an assignment. Predefined contours generally 
describe how work is distributed over time in terms of graphical patterns‮ For exam-
ple, the Bell predefined contour distributes less work to the beginning and end of the 
assignment and distributes more work toward the middle‮ If you were to graph the 
work over time, the graph’s shape would resemble a bell‮
Edit the assignment details directly‮ For example, in the Resource Usage or Task Usage 
view, you can change the assignment values directly in the timescaled grid‮
How you contour or edit an assignment depends on what you need to accomplish‮ 
Predefined contours work best for assignments in which you can predict a likely pattern of 
effort—for example, a task that requires gradual ramp-up time might benefit from a back-
loaded contour to reflect the likelihood that the resource will work the most toward the end 
of the assignment‮
The scenario: At Lucerne Publishing, you’ve been reviewing assignments in the new 
children’s book plan with the assigned resources‮ One of these resources tells you that she 
knows from past experience that the daily work pattern she expects on one of her tasks 
doesn’t match the work pattern on the task as it is currently scheduled‮ You want to update 
the plan to more  accurately model the expected work contour on this assignment‮ You also 
have another  assignment that requires an adjustment‮
C# PDF Image Extract Library: Select, copy, paste PDF images in C#
PDF ›› C# PDF: Extract PDF Image. How to C#: Extract Image from PDF Document. Support PDF Image Extraction from a Page, a Region on a Page, and PDF Document.
c# merge pdf; add pdf files together
VB.NET PDF Text Extract Library: extract text content from PDF
PDF ›› VB.NET PDF: Extract PDF Text. VB.NET PDF - Extract Text from PDF Using VB. How to Extract Text from PDF with VB.NET Sample Codes in .NET Application.
adding pdf pages together; reader combine pdf
230
Chapter 11 Fine-tuning resource and assignment details 
In this exercise, you apply a predefined work contour to an assignment and manually edit 
another assignment‮
In the Task Name column, below task 38, Final review, click the assigned resource 
Carole Poland
On the Task tab, in the Editing group, click Scroll to Task‮
As you can see in the timescaled data at the right, two resources are scheduled to 
work on this task four hours per day (that is, 50 percent of their available working 
time) and a third resource is scheduled to work full time on this task‮ All these assign-
ments have a flat contour—that is, work is distributed evenly over time‮ This is the 
default work contour type that Project uses when scheduling work‮
You want to change Carole Poland’s assignment on this task so that she starts with a 
brief daily assignment and increases her work time as the task progresses‮ To accom-
plish this, you will apply a back-loaded contour to the assignment‮ Note that task 38, 
Final review is a fixed-duration task type, not the default fixed-units task type. This 
task type keeps the task’s duration fixed as you adjust its assignments. 
TIP
If you need a refresher on task types, see “Control task scheduling with task 
types” in Chapter 9, “Advanced task scheduling‮”
On the Format tab, in the Assignment group, click Information‮
The Assignment Information dialog box appears‮ Click the General tab if it is not 
already selected‮
Click the down arrow to display the options in the Work Contour box‮
Applying contours to assignments    
231
11
These are all predefined work contours, and some of the names of the contours are 
graphical representations of a resource’s work over time with that contour applied‮
Select Back Loaded, and then click OK to close the Assignment Information dialog 
box‮
Project applies the contour to this resource’s assignment and reschedules her work 
on the task‮ 
The contour indicator matches the type of
contour applied—back-loaded in this case.
The back-loaded contour causes Project to assign very little work 
to the resource initially and then add more work each day.
You see that in each successive day of the task’s duration, Carole Poland is assigned 
slightly more time to work on the assignment‮ You also see a contour indicator in the 
Indicators column displaying the type of contour that is applied to the assignment‮
In the Indicators column, point to the contour indicator‮
232
Chapter 11 Fine-tuning resource and assignment details 
Project displays a ScreenTip describing the type of contour applied to this 
assignment‮
TIP
Applying a contour to a fixed-duration task will cause Project to recalculate 
the resource’s work value so that the resource works less in the same time period‮ 
For example, Carole’s total work on task 38 was reduced from 20 to 12 hours when 
you applied the contour‮ Depending on the task type, applying a contour to this 
assignment might cause the overall duration of the task to be extended‮ Task 38 is 
a fixed-duration task, so applying the contour did not change the task’s duration. 
For a fixed-work or fixed-unit task, however, it would. If you do not want a contour 
to extend a task’s duration, change the task type (on the Advanced tab of the Task 
Information dialog box) to Fixed Duration before applying the contour‮ 
Next, you will directly edit the assigned work values of another task‮
In the Task Name column, below task 38, Final review, click the assigned resource 
Hany Morcos
Note that Hany is currently assigned four hours per day for each day of the 
assignment’s duration‮ Why four hours? Hany normally has eight working hours 
per day on these particular days (as determined by her resource calendar)‮ She 
was  assigned to this task at 50 percent assignment units, however, so the resulting 
scheduled work is only four hours per day‮
You want to increase Hany’s work on the last two days of this task so that she will 
work full time on it‮ To accomplish this, you will manually edit her assigned work 
values‮
In the timescaled grid in the right pane of the Task Usage view, select Hany Morcos’s 
four-hour assignment for Wednesday, September 2‮
TIP
Point to each day label in the timescale (M, T, W, and so on) and that day’s date 
value will appear in a ScreenTip‮ 
Type 
8h
, and then press the Tab key‮
10 
In Hany’s assignment for Thursday, type 
8h
, and then press Enter‮
Applying contours to assignments    
233
11
Hany is now assigned eight hours per day on Wednesday and Thursday‮ Project 
displays a contour indicator in the Indicators column showing that a manually edited 
contour has been applied to the assignment‮
TIP
If you want to document details about contouring an assignment or anything 
pertaining to an assignment, you can record the details in an assignment note‮ In the Task 
Usage or Resource Usage view, select the assignment, and then click the Notes button in 
the Assignment group on the Format tab‮ Assignment notes are similar to task and resource 
notes‮
Here are a few more capabilities that you can apply in a usage view:
In addition to editing work values manually at the resource level as you did before, 
you can edit work values at the task level‮ When you change a work value at the task 
level, Project adjusts the resulting work value per resource in accordance with each 
resource’s units value on that assignment. For example, assume that on a specific day, 
two resources were assigned four hours each to a task that had a total work value of 
eight hours‮ If you then change the total work on the task for that day to 12 hours, 
Project will increase the work per resource from four to six hours‮
You can split a task in the Gantt Chart view to account for an interruption in the task, 
as you did in Chapter 9‮ You can also split a task in the Task Usage view by enter-
ing “0” work values in the task’s row in the timephased grid for the date range that 
you want‮ To preserve the total work on the task, you should add the same amount 
of work to the end of the task as you subtracted with the split‮ For example, assume 
that a task starts on Monday and has eight hours of total work per day for four days‮ 
Its work pattern (in hours per day) is 8, 8, 8, and 8‮ You interrupt work on the task on 
Tuesday and then add those eight hours to the end of the task (in this case, Friday)‮ 
The new work pattern would be 8, 0, 8, 8, and 8‮
234
Chapter 11 Fine-tuning resource and assignment details 
like you might work in a Microsoft Excel worksheet—you can drag and drop values 
and use the AutoFill handle to copy values to the right or downward‮
Applying different pay rates to assignments
Recall from “Entering multiple pay rates for a resource” earlier in the chapter that you can 
set as many as five pay rates per resource, which allows you to apply different pay rates to 
different assignments for a resource; for example, a different pay rate might depend on the 
skills required for different assignments‮ For each assignment, Project initially uses rate table 
A by default, but you can specify that another rate table should be used‮
The scenario: At Lucerne Publishing, Hany is currently assigned to task 36, Proof and  review, 
as a content editor rather than her default role of a project editor, but her assignment 
still reflects her default pay rate as a project editor. You will apply a different pay rate to 
account for her content editor role on this task‮ Recall that you set up this second pay rate 
for Hany in the “Entering multiple pay rates for a resource” section earlier‮
In this exercise, you change the cost rate table to be applied to an assignment‮
In the Task Name column, below task 36, Proof and review, click the assigned 
resource Hany Morcos
Next, you’ll view the cost of Hany’s assignment‮
On the View tab, in the Data group, click Tables and then click Cost‮
Project displays the Cost table‮ Note the current cost of Hany’s assignment to this 
task: $1,550‮00‮