Troubleshooting cost and resource problems    
355
16
You can see that Hany Morcos and Jane Dow have the largest remaining cost values 
at this point in the plan’s duration‮ Managing costs for these two resources is one way 
you can help limit additional cost variance‮ Note also that Hany’s name is formatted 
red, indicating that she is overallocated‮
On the View tab, in the Task Views group, click Gantt Chart‮
Project displays the Gantt Chart view‮ Next, you’ll look at the tasks to which Hany and 
Jane are assigned‮
If necessary, drag the vertical divider bar to the right to display the Resource Names 
column, and then click the AutoFilter arrow in the Resource Names column heading‮ 
In the menu that appears, click (Select All) to clear all the resource names, and then 
select Hany Morcos and Jane Dow
Click OK‮
Project filters the task list to display tasks to which Hany or Jane is assigned.
Scroll the Gantt Chart view down to show later tasks‮
How to combine pdf files - Merge, append PDF files in C#.net, ASP.NET, MVC, Ajax, WinForms, WPF
Provide C# Demo Codes for Merging and Appending PDF Document
attach pdf to mail merge; batch combine pdf
How to combine pdf files - VB.NET PDF File Merge Library: Merge, append PDF files in vb.net, ASP.NET, MVC, Ajax, WinForms, WPF
VB.NET Guide and Sample Codes to Merge PDF Documents in .NET Project
acrobat combine pdf files; pdf merger online
356
Chapter 16 Getting your project back on track  
Looking at the uncompleted tasks, you can spot Hany Morcos’s overallocation: she’s 
assigned to tasks 37 and 41, which overlap‮ That is why the red overallocated resource 
indicators appear in the Indicators column for these tasks‮
You could fix Hany’s overall allocation by resource leveling, but that is likely to extend 
the project’s finish date and won’t help reduce the project’s overall cost. Instead, 
you’ll replace Hany with a less expensive resource on one of her assignments‮
Click the AutoFilter arrow (shaped like a funnel because the filter is applied) in the 
Resource Names column heading, and in the menu that appears, click Clear Filter 
from Resource Names‮
Project unfilters the task list to show all tasks. 
10 
In the Task Name column, click the name of task 37, Proof and review
This is a task that a less experienced (and cheaper) editor should be able to handle, so 
you’ll replace Hany‮ 
11 
On the Resource tab, in the Assignments group, click Assign Resources‮
The Assign Resources dialog box appears‮ Note the cost of Hany’s assignment to task 
37: $1,550‮
12 
In the Assign Resources dialog box, in the Resource Name column, click Hany 
Morcos, and then click Replace‮
The Replace Resource dialog box appears‮ In this dialog box, you see the total cost 
per resource, based on their cost rates and assignments to tasks in the plan‮
Online Merge PDF files. Best free online merge PDF tool.
RasterEdge C#.NET PDF document merging toolkit (XDoc.PDF) is designed to help .NET developers combine PDF document files created by different users to one PDF
reader merge pdf; pdf combine files online
C# Word - Merge Word Documents in C#.NET
RasterEdge C#.NET Word document merging toolkit (XDoc.Word) is designed to help .NET developers combine Word document files created by different users to one
acrobat reader merge pdf files; .net merge pdf files
Troubleshooting scope-of-work problems    
357
16
13 
In the Resource Name column in the Replace Resource dialog box, click Jun Cao, 
and then click OK‮
Project replaces Hany with Jun on this assignment‮ 
Jun’s lower cost on the assignment, $880, appears in the Assign Resources dialog 
box‮ Note also that the red overallocated resource indicators no longer appear in the 
Indicators column; you have resolved Hany’s overall allocation‮ Finally, note also that 
the finish date of task 37 was moved in by one day. This is due to Jun’s “four by ten” 
working calendar that you set up in Chapter 5, “Setting up resources‮”
14 
In the Assign Resources dialog box, click Close‮
Troubleshooting scope-of-work problems
A project’s scope should include all the work required—and only the work required—to 
deliver the product of the project successfully to its intended customer‮ After project work 
has started, managing its scope usually requires making trade-offs: trading time for money, 
quality for time, and so on‮ You might have the goal of never making such trade-offs, but a 
more realistic goal might be to make the best-informed trade-offs possible‮
The scenario: At Lucerne Publishing, you just consulted with the management (that is, the 
project sponsors)‮ You’ve been asked to shave about $5,000 from the remaining tasks in the 
new children’s book plan. This plan’s finish date is fine as is, but the actual cost has gone 
somewhat over budget‮ You need to reduce work to reduce the remaining costs‮
In this exercise, you view tasks’ remaining costs and remove some tasks from the plan‮
C# PowerPoint - Merge PowerPoint Documents in C#.NET
RasterEdge C#.NET PowerPoint document merging toolkit (XDoc.PowerPoint) is designed to help .NET developers combine PowerPoint document files created by
c# pdf merge; reader create pdf multiple files
C# PDF: C#.NET PDF Document Merging & Splitting Control SDK
C#.NET PDF Merger to Combine PDF Files. Using following C#.NET PDF document merging APIs, you can easily merge two or more independent PDF files to create a
merge pdf online; c# merge pdf
358
Chapter 16 Getting your project back on track  
On the View tab, in the Data group, click Tables, and then click Cost‮
Your focus here is on the tasks not yet completed, so you’ll filter the task list.
On the View tab, in the Data group, click the down arrow next to the Filter box  
(it initially contains [No Filter]) and then click Incomplete Tasks‮
Project filters the task list to show only the tasks that are not yet complete, plus their 
summary tasks‮
One set of tasks in the plan that could be cut without affecting the result of the new 
book plan is task 40 and its subtasks, Design book’s companion website The remain-
ing cost of this work is more than the $5,000 you’ve been asked to cut from the plan‮ 
After consulting with the project’s sponsors, you all agree that this looks like a good 
set of tasks to remove from the plan‮
Select the name of task 40, the summary task Design book’s companion website. 
Do one of the following:
If you are running Project Professional, continue with step 5‮
If you are running Project Standard, skip ahead to step 6‮
TIP
Not sure which edition of Project you have? Here’s one easy way to tell‮ The 
Project application title bar includes “Project Professional” or “Project Standard‮” You 
can also see your edition identified in the Account screen of the Backstage view. (To 
check this, click File, click Account, and then look for your edition name on the right 
side of the Account pane‮)
C# PDF File Split Library: Split, seperate PDF into multiple files
Split PDF document by PDF bookmark and outlines. Also able to combine generated split PDF document files with other PDF files to form a new PDF file.
acrobat merge pdf; reader create pdf multiple files
VB.NET Word: Merge Multiple Word Files & Split Word Document
As List(Of DOCXDocument), destnPath As [String]) DOCXDocument.Combine(docList, destnPath) End imaging controls, PDF document, image to pdf files and components
combine pdfs online; acrobat merge pdf files
Troubleshooting scope-of-work problems    
359
16
On the Task tab, in the Schedule group, click Inactivate‮
Project inactivates the summary task and its subtasks‮
In Project Professional, inactivated tasks appear like this.
IMPORTANT
If you need a refresher on inactivating tasks in Project Professional, see 
Chapter 12, ”Fine-tuning the Project plan‮”
These inactivated tasks will remain in the plan, but they have no scheduling or cost 
impact now‮ Note that the Remaining cost value for task 0, the project summary 
task, and for task 27, the Design and Production summary task, are correspondingly 
reduced‮
NOTE
Project Professional users should skip to the end of this procedure‮ Project 
Standard users proceed from step 4 directly to step 6‮
With the name of task 40 selected, right-click and in the shortcut menu that appears, 
click Delete Task‮
A Planning Wizard message might appear, asking you to verify that you want to 
delete this summary task and its subtasks‮ If it appears, make sure that Continue is 
selected and then click OK‮
Project deletes the summary task and its subtasks and renumbers the remaining 
tasks‮
VB.NET TIFF: Merge and Split TIFF Documents with RasterEdge .NET
String], docList As [String]()) TIFFDocument.Combine(filePath, docList powerful & profession imaging controls, PDF document, tiff files and components
best pdf combiner; pdf merger online
VB.NET TIFF: .NET TIFF Merger SDK to Combine TIFF Files
VB.NET TIFF merging API only allows developers to combine two source powerful & profession imaging controls, PDF document, image to pdf files and components
merge pdf; append pdf files reader
360
Chapter 16 Getting your project back on track  
After deleting tasks, subsequent tasks are renumbered.
Note that the Remaining cost value for task 0, the project summary task, and for task 
27, the Design and Production summary task, are correspondingly reduced‮
You confer with the project sponsors, who are pleased that you can wrap up the new book 
project at a lower cost‮ Although completing the remaining work within the given time and 
cost constraints will be a challenge, you’re optimistic about the project’s future performance 
given your project management skills and knowledge of Project‮
+
CLEAN UP
Close the Back on Track file.
Key points
When addressing variance in a plan, you’ll find it useful to evaluate your plan (and 
variance) in terms of time, cost, and scope: the three sides of the project triangle‮
When addressing schedule problems, focus your remedies on tasks on the critical 
path; these drive the finish date of the project.
When addressing cost or scope problems, focus on expensive resources—especially 
on their longer assignments‮
In-Depth and 
Special Subjects
17 Applying advanced formatting 
and printing 
362
18 Advanced report formatting 
388
19 Customizing Project 
416
20 Sharing information with other programs 442
21 Consolidating projects and resources 
468
Chapter at a glance
Define
Add more details to a Gantt chart view, 
page 364‮
Customize
Customize text and task bars in a Timeline 
view, page 371‮
Change
Change the details in a Network Diagram 
view, page 373‮
Export
Print views, and generate PDF or XPS files, 
page 381‮
17
363
IN THIS CHAPTER, YOU WILL LEARN HOW TO
Customize a Gantt chart view‮
Format a Timeline view‮
Adjust details shown in nodes of a Network Diagram view‮
Add additional bar types to a Calendar view‮
Adjust printing options, and generate a PDF or XPS snapshot of views‮
This chapter introduces you to some of the more advanced formatting features in 
Microsoft Project 2013‮ A well-formatted plan can be valuable when communicating de-
tails to  resources, customers, and other stakeholders. Some of the formatting capabilities 
in Project are similar to those of a style-based word processor, such as Microsoft Word, 
in which  defining a style once affects all content in the document to which that style has 
been  applied. In Project, you can use styles to change the appearance of a specific type of 
Gantt bar, such as a summary bar, throughout a plan‮ Other formatting options introduced 
in this chapter focus on direct formatting of tasks and formatting some of the more com-
monly used views‮ In this chapter, you’ll apply some of Project’s more advanced formatting 
features to views‮
PRACTICE FILES
Before you can complete the exercises in this chapter, you need to copy 
the book’s practice files to your computer. A complete list of practice files is provided in 
“Download the practice files” at the beginning of this book. For each exercise that has a 
practice file, simply browse to where you saved the book’s practice file folder.
IMPORTANT
If you are running Project Professional with Project Web App/Project Server, take 
care not to save any of the practice files you work with in this book to Project Web App (PWA). For 
more information, see Appendix C, “Collaborating: Project, SharePoint, and PWA‮”
Applying advanced 
formatting and printing
364
Chapter 17 Applying advanced formatting and printing 
Formatting a Gantt chart view
You can format specific items (a milestone, for example) in a Gantt chart view to change 
the appearance of that item‮ If you completed Chapter 7, “Formatting and sharing your 
plan,” you worked with Gantt chart styles and direct formatting of Gantt bars‮ In this sec-
tion, you will work with bar styles to change the visual appearance of specific types of Gantt 
bars (such as summary tasks) and other elements (such as deadline indicators) in ways that 
the Gantt chart styles cannot‮ The format changes you make apply only to the active view‮
TIP
Remember that several views are Gantt chart views, even though only one view is 
specifically called the Gantt Chart view‮ Other Gantt chart views include the Detail Gantt, 
Leveling Gantt, Multiple Baselines Gantt, and Tracking Gantt‮ The term Gantt chart 
view generally refers to a type of presentation that shows Gantt bars organized along a 
timescale‮
In addition to changing the formatting of items that can appear in a Gantt chart view 
(such as a task’s Gantt bar), you can add or remove items‮ For example, it might be  useful 
to  compare baselineinterim, and scheduled plans in a single view‮ Doing so helps you 
evaluate the schedule adjustments you have made‮
Scenario: At Lucerne Publishing, you’re managing a book project that is now  underway‮ For 
this project, you are tracking progress closely and have found value in  showing the team a 
view that compares current progress with a baseline plan‮ Now you’d like to add an interim 
plan to this view because the interim plan is more timely than the original baseline‮
In this exercise, you customize a Gantt chart view with a custom bar style‮
SET UP
You need the Advanced Formatting_Start file located in your Chapter17 
practice file folder to complete this exercise. Open the Advanced Formatting_Start file, 
and save it as Advanced Formatting. 