A Work Breakdown Structure for Implementing and Costing an ERP Project 
Communications of the IBIMA 
Volume 6, 2008  
94 
A Work Breakdown Structure for Implementing and Costing an ERP Project 
Aisha Momoh, Decision Engineering Centre, Cranfield University, Bedford, UK,a.momoh@cranfield.ac.uk 
Rajkumar Roy, Decision Engineering Centre, Cranfield University, Bedford, UK, r.roy@cranfield.ac.uk                                    
Essam Shehab, Decision Engineering Centre, Cranfield University, Bedford, UK,e.shehab@cranfield.ac.uk 
Abstract 
This  paper  presents  a  Work  Breakdown  Structure 
(WBS) for a phased implementation of an Enterprise 
Resource Planning (ERP) solution. The key activities 
that  constitute  an  ERP  implementation  project  are 
discerned in detail, each in its entirety.  Each activity 
illustrates the tasks  required  to  fulfill  each  part  of  a 
project.      The  potential  challenges  that  are  usually 
encountered  in  every  selected  activity are discussed.  
Finally,  using  a  WBS  to  cost  an  ERP  project  is 
proposed.  
Keywords:  Work Breakdown Structure; WBS; ERP; 
Project Activities 
1.  Introduction 
ERP  has  been  referred  to  as  a  business  operating 
system  that  enables  better  resource  planning  and 
improved  delivery  of  value-added  products  and 
services  to  customers  [10].    They  automate  core 
corporate  activities  such  as  manufacturing  and  the 
management  of  financial,  and  human  resources  and 
the supply chain [10].  Major business drivers behind 
ERP  implementations  are:  improving  productivity, 
providing  competitive  advantage,  and  satisfying 
customer demands [5].  
Although ERP applications have been widely adopted 
by  a  variety  of  industries  worldwide,  the challenges 
faced  during  and  post-implementation  remain  a 
growing concern.  ERP systems are complex pieces of 
software 
[5]. 
Consequently, 
many 
such 
implementations have been difficult, lengthy and over 
budget, were terminated before completion, and failed 
to achieve their business objectives even a year after 
implementation  [5].    Researchers  and  practitioners 
alike  are  still  in  the  process  of  studying  and 
understanding the causes of these hurdles.  As part of 
this research, an in-depth literature review highlighted 
numerous  project  challenges.    Based  on  the  Risk 
Factors of ERP, one of the risks identified in project 
management and control, is a lack of effective project 
management methodology [4].  However, very little is 
mentioned about ERP project planning methodologies 
in  research.   Based on the primary author’s  in-depth 
experience  in  ERP  implementations,  predominantly 
SAP, she recognizes that some project methodologies 
are not detailed enough.  Regardless of how effective 
a methodology may appear, should it lack the relevant 
detail,  the  project  in  question  may  not  yield  the 
anticipated success.  In order to achieve a successful 
implementation, this paper proposes the use of a work 
breakdown structure (WBS) to guide an ERP project. 
 Work  Breakdown  Structure  is  a  project 
management tool.  It is defined as an enumeration of 
all  work  activities  in  hierarchic refinement  of  detail 
which  organizes  work  to  be  done  into  short 
manageable  tasks  with  quantifiable  inputs,  outputs, 
schedules, and assigned responsibilities [14].   A WBS 
is also used for project costing.  This paper discusses 
using a WBS to organize an ERP project, 
Literature  review  reveals  that  ERP  implementations 
are  fraught  with  numerous  problems.  ERP 
implementations are notorious for taking a longer time 
and taking more money than is projected [12].  Most 
of  the  literature  studied  indicates  a  variety  of  issues 
inherent in executing an ERP project.  However, there 
is hardly any mention of failures based on poor project 
planning and methodology.   Based  on  in-depth  ERP 
experience and use of various project methodologies, 
the primary author recognizes that several projects fail 
as a consequence of poor planning.  This area requires 
significant attention.   
2.  Research Methodology 
The methodology that was employed in this research 
was based on the following: 
•  Information gathered on company-specific  
project 
methodologies, 
ERP 
implementations,  Accelerated  SAP  (ASAP) 
project  methodology  used  in  SAP  R/3 
projects  and  Work  Breakdown  Structures 
based  on  primary  author’s  ERP  project 
experience. 
•  Literature review on ASAP 
Pdf rearrange pages online - re-order PDF pages in C#.net, ASP.NET, MVC, Ajax, WinForms, WPF
Support Customizing Page Order of PDF Document in C# Project
how to rearrange pages in a pdf file; change pdf page order preview
Pdf rearrange pages online - VB.NET PDF Page Move Library: re-order PDF pages in vb.net, ASP.NET, MVC, Ajax, WinForms, WPF
Sort PDF Document Pages Using VB.NET Demo Code
how to rearrange pdf pages; reorder pdf page
Aisha Momoh,Rajkumar Roy and Essam Shehab 
Communications of the IBIMA 
Volume 6, 2008  
95 
•  Identifying  project  activities  that  are 
excluded from ASAP based on knowledge of 
company-specific project methodologies. 
•  Using  a  WBS to  amalgamate  the  identified 
project  activities  with  the  ASAP  project 
activities 
•  Based on literature review of ERP challenges 
and  previous  case  study,  identifying 
challenges  associated  with  each  project 
activity in the WBS. 
3.  ASAP Project Methodology 
SAP  introduced  the  ASAP  implementation 
methodology  with the  goal  of speeding up SAP 
implementation 
projects 
[9]. 
ASAP 
implementation  is  a  structured  implementation 
approach that can help managers achieve a faster 
implementation  with  quicker  user  acceptance, 
well-defined 
roadmaps, 
and 
efficient 
documentation at various phases [9].   The ASAP 
methodology phases are [9]: 
•  Project  preparation  –  the  purpose  of  this 
phase  is  to  provide  initial  planning  and 
preparation of the SAP project.  The steps of 
this phase help identify and plan the primary 
focus  areas  to  be  considered  such  as:  
objectives,  scope,  plan  and  definition  of 
project  team.    The  outcome  is  the  project 
charter. 
•  Business  blueprint  –  the  purpose  of  this 
phase  is  to  create  the  business  blueprint, 
which  is  a  detailed  documentation  of  the 
organizational  structure  and  business 
processes  gathered  during  requirements 
workshops/meetings.    It  will  allow  the 
implementation project team to clearly define 
their  scope,  and  only  focus  on  the  SAP 
processes  needed  to  run  the  organization 
business. 
•  Realisation – the purpose of this phase is to 
actually  configure  SAP  R/3  based  on  the 
specifications  of  the  business  blueprint  as 
well  as  taking  further  input  into  account 
(Questions  and  Answer  database).    The 
objective  is  the  final  configuration  of  the 
system, an overall test, and the release of the 
system for live operation. 
•  Final  preparation  –  the  purpose  of  this 
phase  is  to  complete  the  final  preparation, 
including  testing,  end  user  training,  system 
management and cutover activities.  The final 
preparation  phase  also  serves  to  resolve  all 
open issues. 
•  Go  live  and  support –  the  purpose  of  this 
phase  is  to  move  from  a  pre-production 
environment  to  live  operation.    A  support 
organization must be set up for end users to 
provide long-term support.  This phase is also 
used  to  monitor  system  transactions  and  to 
improve  overall  system  performance.  
Finally, the completed project is closed. 
Each phase is composed of a group of work packages 
[9]. These work packages are structured in activities, 
and each activity is composed of a group of tasks [9]. 
For each task, a definition, a set of procedures, results 
and  roles  are  provided  in  the  ASAP  methodology 
documentation  [9]. Implementations where ASAP  or 
Powered by  SAP methodologies were used  averaged 
only 8 months, compared to 15 months  for  standard 
implementations [9].  
4.  Work  Breakdown  Structure  for  ERP 
Implementation 
 complex  project  is  made  manageable  by  first 
breaking  it  into  individual  components  in  a 
hierarchical  structure,  known  as  Work  Breakdown 
Structure [13].  Such a structure defines tasks that can 
be completed independently of other tasks, facilitating 
resource allocation, assignment of responsibilities, and 
measurement and control of the project [13].  
This section depicts the use of a WBS in Figures 1, 1a 
and 1b to plan an ERP project.  The various levels in 
the WBS are illustrated in Table 1.   
C# TIFF: How to Reorder, Rearrange & Sort TIFF Pages Using C# Code
C# TIFF - Sort TIFF File Pages Order in C#.NET. Reorder, Rearrange and Sort TIFF Document Pages in C#.NET Application. C# TIFF Page Sorting Overview.
how to move pages in pdf converter professional; reverse page order pdf online
Online Merge PDF files. Best free online merge PDF tool.
Then press the button below and download your PDF. By dragging your pages in the editor area you can rearrange them or delete single pages.
how to reorder pdf pages in; how to move pages in a pdf
A Work Breakdown Structure for Implementing and Costing an ERP Project 
Communications of the IBIMA 
Volume 6, 2008  
96 
Fig 1. WBS for ERP Implementation                 
VB.NET TIFF: Modify TIFF File by Adding, Deleting & Sort TIFF
you want to change or rearrange current TIFF &ltsummary> ''' Sort TIFF document pages in designed powerful & profession imaging controls, PDF document, image
how to reorder pages in pdf online; rearrange pdf pages in reader
VB.NET PDF File & Page Process Library SDK for vb.net, ASP.NET
a PDF document which is out of order, you need to rearrange the PDF you with examples for adding an (empty) page to a PDF and adding empty pages to a
rearrange pdf pages; moving pages in pdf
Aisha Momoh,Rajkumar Roy and Essam Shehab 
Communications of the IBIMA 
Volume 6, 2008  
97 
Fig 1a.  WBS for ERP Implementation 
C# PowerPoint - How to Process PowerPoint
the simplest procedures, for instance, using online clear C# out useless PowerPoint document pages simply with solution to sort and rearrange PowerPoint slides
change pdf page order; how to move pages in pdf files
VB.NET Word: How to Process MS Word in VB.NET Library in .NET
well programmed Word pages sorter to rearrange Word pages in extracting single or multiple Word pages at one & profession imaging controls, PDF document, image
how to reorder pages in pdf reader; pdf move pages
A Work Breakdown Structure for Implementing and Costing an ERP Project 
Communications of the IBIMA 
Volume 6, 2008  
98 
Fig 1b.  WBS for ERP Implementation 
Table 1 below illustrates the various levels of project 
activity  in  the  WBS  structures  above.    Each 
organization uses its own terminology for classifying  
WBS  components  according  to  their  level  in  the 
hierarchy [13].  For example, some organizations refer 
to  different  levels  as  tasks,  sub-tasks  and  work 
packages,  whilst  others use  the terms phases, entries 
and activities [13].   In this paper, activities are used to 
classify the WBS components.  The nodes (in circles) 
A and B indicate continuation of the activities linked  
to these nodes 
Table 1:  WBS Component Levels  
Project 
First Level 
Activity 
Second Level Activity 
Third Level Activity 
ERP 
Implementation 
Project Preparation  Define Project Scope and 
Objectives 
Identify Project Team 
Identify Stakeholders 
System 
Architecture 
Design 
Identify System Environment  Technical Infrastructure 
Preparation 
Identify Development 
Environment 
Identify Quality 
Assurance Environment 
Identify Training 
Environment 
Identify Production 
Environment 
Business Blueprint  AS-IS Business Process 
Analysis 
Identify End-to-End 
Current Business 
Processes 
Identify Process 
Integration Points 
Map ERP Processes to 
Business Processes 
Process Images in Web Image Viewer | Online Tutorials
used document types are supported, including PDF, multi-page easy to process image and file pages with the deleting a thumbnail, and you can rearrange the file
how to move pages in a pdf file; pdf rearrange pages
VB.NET PowerPoint: Sort and Reorder PowerPoint Slides by Using VB.
page will teach you to rearrange and readjust amount of robust PPT slides/pages editing methods and powerful & profession imaging controls, PDF document, image
pdf reverse page order online; reorder pages in a pdf
Aisha Momoh,Rajkumar Roy and Essam Shehab 
Communications of the IBIMA 
Volume 6, 2008  
99 
Project 
First Level 
Activity 
Second Level Activity 
Third Level Activity 
Define TO-BE Processes 
Define End-to-End 
Future Business 
Processes 
Identify Gaps 
Propose Gap Solution 
Define Reports 
Define Programs 
Define Interfaces 
Define Manual 
Processes 
Document Blueprint 
Sign Off Blueprint 
Configuration and 
Development 
Configure Solution 
Write Unit Test Scripts 
Configure Solution 
Unit test Configuration 
Develop Code for Identified 
Gaps 
Write Technical 
Specifications 
Write Unit Test Scripts 
Unit Test 
Programs/Reports/Interf
aces 
Sign Off Configuration and 
Development 
Define 
Authorizations 
Define Roles in Organisation   
Identify Roles for Use of 
ERP 
Define Authorisations 
Test Authorisations 
Sign Off Authorisations 
Data Conversion 
Define Fields in ERP 
Solution 
Map ERP Fields to Legacy 
System Fields 
Convert Legacy Fields to 
ERP Fields 
Define Data for Cleansing 
Cleanse Data 
Sign Off Data Cleansing 
Data Migration 
Program 
Development 
Develop Migration Program   
Unit Test Migration Program   
Sign Off Data Migration 
Program 
System Testing 
Define Test Scripts 
Test ERP Solution End-to-
End 
Sign Off System Tests 
Training 
Define Business Processes 
Based on Roles 
A Work Breakdown Structure for Implementing and Costing an ERP Project 
Communications of the IBIMA 
Volume 6, 2008  
100 
Project 
First Level 
Activity 
Second Level Activity 
Third Level Activity 
Document Training  
Train Users on Business 
Processes 
Train Users on ERP 
User Acceptance 
Testing 
Define Business Scenarios 
User Acceptance Test 
Documents 
Create Fault Report 
Sheet 
Define User Acceptance Test 
Scripts 
Test ERP functionality  
Sign Off 
Cutover 
Migrate Cleansed Data 
Go Live 
5.  WBS Activities and Potential Challenges 
The WBS project activities in table 1 will be described 
in  this  section.    They  have  been  derived  from  the 
ASAP  project  methodology,  literature  review  on 
project  methodologies  and  SAP  implementation 
experience.    Certain  activities  that  are  already 
embedded as sub-tasks in ASAP project activities are 
illustrated  as  First  Level  activities  for  transparency 
and  more  effective  planning.    Such  activities  are 
System Architecture Design, Define  
Authorizations,  Data  Conversion,  Data  Migration 
Program Development, System Testing, Training, and 
User Acceptance Testing. First Level activities will be 
the  focus  of  this  section  as  well  as  the  potential 
challenges that could emerge during the execution of 
each activity.   
Project Preparation 
This  activity  has  been  defined  in  section  4  of  this 
paper.    Some  of  the  challenges  that  may  present 
themselves in project management and control, which 
is  part  of  project  preparation,  are:  (i)  lack  of 
agreement  on  project  goals,  (ii)  lack  of  senior 
management involvement, and (iii) a lack of effective 
project management methodology [4]. 
System Architecture Design 
The essence of this activity is to agree on and define 
the environment upon which the ERP application will 
be installed.  At this stage, the environments in which 
the application will be configured, quality assured and 
operate  in  a  live  situation  are  also  critical 
considerations.  Furthermore, even though the project 
team is not responsible for the technical infrastructure, 
it  is  essential  that  it  is  flagged  in  the  WBS  as  a 
dependency. 
Potential  challenges  in  this  activity  are:  (i) 
unavailability  of  technical  infrastructure,  (ii) 
technology  complexity[4],  (iii)  failure  in  attempt  to 
link  legacy  applications,  (iv)  and  minimal 
understanding  of  architecture  requirements  and 
design. 
Business Blueprint 
This activity  has been  described in section  4  of  this 
paper.  Some of the likely potential challenges during 
the  execution  of  this  activity  are:  (i)  minimal 
understanding  of  business  processes,  (ii)  business 
requirements  to  customize  the  ERP  application 
beyond its standard functionality, (iii) lack of business 
process  reengineering,  (iv)  employee  resistance  to 
change, (v) use of inexperienced consultants, and (vi) 
minimal  understanding  of  the  ERP  application 
functionality.   Further challenges are being unable to 
comply  with  the  standard  which  ERP  software 
supports, and a lack of integration between enterprise-
wide systems [4]. 
Configuration and Development 
This activity  is  equivalent  to  the  Realisation  part  of 
the  ASAP methodology.  It  involves configuring  the 
ERP application based on the business blueprint.  It is 
essential  the  application  is  configured  using  to  the 
standard functionality in the system.  Other activities 
under  the  umbrella  of  this  main  activity  are  the 
development  of  reports,  interfaces  and  additional 
programs. 
Aisha Momoh,Rajkumar Roy and Essam Shehab 
Communications of the IBIMA 
Volume 6, 2008  
101 
Some  of  the likely challenges in  this activity are: (i) 
unclear  and  misunderstanding  of  changes  in 
requirements,  (ii)  lack  of  an  effective  methodology, 
and  (iii)  poor  estimation  and  failure  to  perform  the 
activities  needed  [4].    Customization  is  usually 
associated  with  increased  IS  costs,  longer 
implementation time, and the inability to benefit from 
vendor  software  maintenance,  and  upgrades  [5].  
Another key  challenge is  a lack  of  understanding  of 
the ERP application by the consultants.  Additionally, 
lack of resources represents a major concern in ERP 
implementation [5]. 
Define Authorizations 
The purpose of this activity is to define the roles of the 
respective ERP application users once the application 
has  gone  live.    These  roles  will  be  used  to  define 
access  rights  for  each  of  the  users.    This  way, 
unauthorized  users  will  not  be  allowed  access  to 
information in the ERP application that is not within 
their jurisdiction.  The main challenge in this activity 
is incorrect definition of roles and authorizations. 
Data Conversion 
This  activity  involves  converting  the  format  of  the 
data in the legacy system to suit the data format of the 
ERP  system.  This process also entails cleansing the 
data in the legacy system.  This means that the users 
will  filter  through  the  data  in  their  old  system,  and 
eradicate any discrepancies. 
A  fundamental  requirement  for  the  effectiveness  of 
ERP  system  is  the  availability  and  timeliness  of 
accurate  data  [5].    They  further  advise  that  the 
management of  data entering the system is a  critical 
issue throughout system implementation.  Data-related 
challenges include finding the proper data to load into 
the  system  and  converting  disparate  data  structures 
into a single, consistent format before system use [5].   
Data Migration Program Development 
The  Data  Migration  Program  Development  activity 
involves coding the program that will transfer the data 
from  the  legacy  system  to  the  ERP  application.  
Potential challenges that could be presented during the 
execution of this activity are: (i) lack of coding skills, 
and (ii) improperly defined data. 
System Testing 
System  Testing  entails  the  consultants  that 
implemented  the  ERP  application  ensuring  that  the 
system works end-to-end.  The entire system is tested, 
process by process across all functions of the system. 
The  type  of  challenges  that  may  be  faced  during 
system  testing  are:  (i)  discovering  that  a  substantial 
amount of the configured functionality does not meet 
business  requirements, (ii) allowing scope creep  due 
to  sudden  changes,  (iii)  the  tendency  to  carry  on 
testing  beyond  its  specified,  and  (iv)  lack  of 
understanding of the ERP application. 
Training 
Training  involves  imparting  knowledge  of  the 
implemented solution  to  the  users  before the  system 
goes into live operation.  This activity entails defining 
business  processes  for  the  respective  roles  and 
defining  business  scenarios  to  suit  these  processes.  
These  scenarios  enable  the  users  to  understand  the 
system functionality better. 
Insufficient training of end users could be a potential 
challenge  during  the  Training  exercise  [4].    Other 
potential challenges are: (i) lack  of user commitment 
and  ineffective  communication  with  users,  and  (ii) 
conflicts between user departments [4]. 
User Acceptance Testing (UAT) 
This activity involves the users whom will utilize the 
ERP application in a live environment, ensuring that 
all  the  business  requirements  are  met  in  the  system 
and  are  functional.    The  users  define  business 
scenarios for testing. 
Potential  challenges  in  UAT  are:  (i)  lack  of  user 
training,  (ii)  lack  of  understanding  of  the  business 
processes  and  requirements,  and  (iii)  resistance  to 
change. 
Cutover 
This activity means going live by migrating from the 
legacy  system  to  the  ERP  application.    This 
application  becomes  operational  in  a  live 
environment.  It involves migrating live data from the 
legacy system to the new system. 
Typical  challenges  that  may  be  presented  whilst 
executing  this  activity  are:  (i)  unavailability  of  a 
complete set of data for migration, (ii) failure of data 
migration  program,  (iii) unavailability  of  operational 
environment for data to be migrated into, and (iv) lack 
of business readiness. 
6.  Discussions and Conclusion 
Researchers  and  practitioners  concede  that  ERP 
implementations  are  fraught  with  problems.  
Literature review reaffirms this fact, and illustrates a 
A Work Breakdown Structure for Implementing and Costing an ERP Project 
Communications of the IBIMA 
Volume 6, 2008  
102 
variety of ERP implementation challenges.  However, 
not  much  is  mentioned  about  poor  project  planning 
being  one  of  the  challenges  encountered  in  ERP 
project execution.  The methodologies used in project 
planning and the way that they are used go a long way 
in determining the success or failure of a project. 
A good project methodology known as ASAP, which 
is  used  in  SAP  implementations,  was  studied.  
However, in order to ensure that all aspects of an ERP 
implementation are addressed, it is advisable to extend 
ASAP  and  other  methodologies  into  a  WBS.    The 
WBS will be used to define the ERP project activities 
so that  the  lowest level of  activity is  accounted  for.  
This paper  illustrated  the  use of  a  WBS  in defining 
project activities.   Additionally,  based  on a  previous 
case  study  and  literature  review, the  challenges  that 
likely to be encountered in ERP implementations were 
highlighted.   Going  forward, further  research  should 
be  conducted  to  link  these  challenges  to  the  WBS 
using  a  Risk  Breakdown  Structure  (RBS).    This 
exercise will guide an organization implementing ERP 
against  the  potential  risks  that  are  likely  in  project 
activities.  
 further  area  for  research  is  the  costing  of  ERP 
project  activities  using  a  WBS.    This  will  guide 
organizations  in  preparing  realistic  budgets  for  their 
ERP implementations.   
7.  References 
[1]  Kovacs,  G.L.,  Paganelli,  P.    “A  Planning  and 
Management  Infrastructure  for  Lare,  Complex, 
Distributed  Projects  –  Beyond  ERP  and  SCM”, 
Computers in Industry (51), 2003, pp. 165-183.                 
[2]  Wei,  C.,  Wang,  M.J.  “A  Comprehensive 
Framework  for  Selecting  an  ERP  System”, 
International  Journal  of  Project  Management  (22), 
2004, pp. 161-169. 
[3] Labuschagne, C., Brent, A.C. “Sustainable Project 
Life  Cycle  Management:  the  Need  to  Integrate  Life 
Cycles  in  the  Manufacturing  Sector”,  International 
Journal  of Project Management (23), 2005,  pp. 159-
168. 
[4] Huang, S.,  Chang,  I., Li,  S.,  Lin,  M. “Assessing 
Risk  in  ERP  Projects:  Identify  and  Prioritize  the 
Factors”,  Industrial  Management  &  Data  Systems 
(104:8), 2004, pp. 681-688. 
[5]  Somers,  T.M.,  Nelson,  K.G.  “A  Taxonomy  of 
Players  and  Activities  Across  the  ERP  Project  Life 
Cycle”, Information and Management (41), 2004, pp. 
257-278. 
[6] Daneva, M. @Lessons Learnt from Five Years of 
Experience  in  ERP  Requirements  Engineering”, 
Proceedings  of  the  11
th
IEEE  International 
Requirements Engineering Conference, 2003. 
[7]  Gable,  G.G.,  Scott,  J.E.,  Davenport,  T.D. 
“Cooperative 
ERP 
Life-Cycle 
Knowledge 
Management”,  Proceedings  of  the  Ninth  Australian 
Conference  on  Information  Systems,  September  – 
October 1998, pp. 227-240. 
[8] Leopoulos, V., Kirytopoulos, K., Voulgaridou, D. 
“ERP  Systems  as  a  Component  of  the  Electronic 
Supply  Chain:  Classification  of  Implementation 
Risks”,  Proceedings  of  the  2005  International 
Conference  on  computational  Intelligence  for 
Modelling, Control and Automation, and International 
Confe  Intelligent  Agents,  Web  Technologies  and 
Internet Commerce, 2005. 
[9]  Esteves,  J.,  Chan,  R.,  Pastor,  J.,  Rosemann,  M. 
“An  Exploratory  Study  of  Knowledge  Types 
Relevance Along Enterprise Systems  Implementation 
Phases”, 4
th
European Conference on Organizational 
Knowledge and Learning Capabilities, April 2003. 
[10]  Chang,  S.  “ERP  Life  Cycle  Implementation, 
Management  and  Support:  Implications  for  Practice 
and  Research”,  Proceedings  of  the  37
th
Hawaii 
International Conference on System Sciences, 2004. 
[11]  Esteves,  J.,  Pastor,  J.A.  “A  Framework  to 
Analyse  Most  Critical  Work  Packages  in  ERP 
Implementation  Projects”,  International  Conference 
on Enterprise Information Systems, 2002. 
[12] Mabert, V.A., Soni,  A.,  Venkataramanan,  M.A. 
“Enterprise  resource  planning  survey  of  US 
manufacturing  firms”,  Production  and  Inventory 
Management Journal (41:2), 2000, pp. 52-58. 
[13] Work Breakdown Structure. 
Retrieved June 7, 2008, 
from:
//www.netmba.com/operations/project/wbs/ 
[14]  Tausworthe,  R.C.  The  Work  Breakdown 
Structure in Software Project Management.      
Retrieved June 8, 2008, 
from://md1.csa.com/partners/viewrecord.php?requeste
r=gs&collection=TRD&recid=A8133550AH&q=Wor
k+Breakdown+Structure+Tausworthe&uid=79289263
1&setcookie=yes 
Aisha Momoh,Rajkumar Roy and Essam Shehab 
Communications of the IBIMA 
Volume 6, 2008  
103 
Copyright  ©  2008  by  the  International  Business 
Information  Management  Association  (IBIMA).   All 
rights  reserved.   Authors  retain  copyright  for  their 
manuscripts  and  provide  this  journal  with  a 
publication permission agreement as a part of IBIMA 
copyright  agreement.   IBIMA  may  not  necessarily 
agree with the content of the manuscript.  The content 
and proofreading of this manuscript as well as and any 
errors are the  sole responsibility  of its author(s).  No 
part or all of this work should be copied or reproduced 
in  digital,  hard,  or  any  other  format  for  commercial 
use without written permission.  To purchase reprints 
of this article please e-mail: admin@ibima.org
.  