Appendices 
Within Year 1 
Implementation Milestone
: Within one year of incidental take authorization, the Implementation 
Team shall setup the hotline number (E-10), and shall design and implement the jurisdictional 
tracking system. (M-1, 2)   
Within No Survey Areas, (a) Develop telephone tech support for the general public to deal with 
free-roaming tortoises; and (b) Free roaming tortoises should be made available for research, 
education, captive breeding, zoo placement, adoption through recognized organizations (e.g. 
California Turtle and Tortoise Club); or, if clinically ill, dealt with in a manner consistent with 
the Berry Salvage Protocol. (E-10) 
Incidental take authorized by the Plan is necessarily attached to existing political infrastructure.  
For example, the Plan would authorize projects subject to discretionary permits but would not 
track projects subject to ministerial permits. It is important that authorized and unauthorized 
ground disturbance is tracked by the Plan to determine actual loss of habitat relative to the 1% 
Allowable Ground Disturbance.  Agricultural development in DWMAs, which is not currently 
covered by the Plan, must be tracked to determine its relative impact, if any.  It is generally 
understood that aerial photographs would be used, in conjunction with reports from participating 
jurisdictions, to track these forms of ground disturbance. (No #) 
Feral Dog Management Plan
Within Year 2 
Implementation Milestone
: Within two years of the record of decision, the Implementation 
Team, BLM, county animal control, and other applicable entities shall develop a Feral Dog 
Management Plan (FDMP). (DT-5) 
Within Year 3 
Implementation Milestone
: Within three years of the record of decision, if feral dogs are shown 
to be a significant threat to tortoises and other covered species, the earliest phase(s) of the FDMP 
shall be implemented. (DT-5) 
Cannot select text in pdf - search text inside PDF file in C#.net, ASP.NET, MVC, Ajax, WinForms, WPF
Learn how to search text in PDF document and obtain text content and location information
pdf select text; pdf text search
Cannot select text in pdf - VB.NET PDF Text Search Library: search text inside PDF file in vb.net, ASP.NET, MVC, Ajax, WinForms, WPF
Learn How to Search Text in PDF Document and Obtain Text Content and Location Information in VB.NET application
search pdf documents for text; how to select text in pdf and copy
Appendices 
NEW MEASURES TO BE IMPLEMENTED: BUREAU OF LAND 
MANAGEMENT 
Fencing: Open Areas
Within Year 2 
Implementation Milestone:
Within two years of the record of decision, the BLM shall work with 
the Implementation Team to determine the specific location along Camp Rock Road to install the 
fence, determine educational outreach needs, and develop a monitoring protocol. (E-7) 
A standard fence will be placed along pertinent portions of the western boundary of the Johnson 
Valley Open Area to prevent OHV use in the Ord-Rodman DWMA to the west and to minimize 
use in the Cinnamon Hills. (DT-23) 
The Plan proposes installation of new fences to counteract the effects of Johnson Valley and 
Stoddard Valley on tortoise populations in the Ord-Rodman DWMA.  As with the recently 
installed fences around the El Mirage Open Area and along the Mojave-Randsburg Road, 
monitoring will be needed to cure intentional vandalism of the fences. Educational outreach will 
be a high priority at the time of fencing and thereafter. The desired effects are to reduce tortoise 
mortality and begin to repair degraded habitats (i.e., in the Cinnamon Hills and southern portions 
of the Ord-Rodman DWMA coinciding with northern Lucerne Valley), which should be 
monitored and adaptive management applied, as needed. (DT-23) 
Feral Dog Management Plan
Within Year 2 
Implementation Milestone
: Within two years of the record of decision, the Implementation 
Team, BLM, county animal control, and other applicable entities shall develop a Feral Dog 
Management Plan (FDMP). (DT-5)   
Within Year 3 
Implementation Milestone
: Within three years of the record of decision, if feral dogs are shown 
to be a significant threat to tortoises and other covered species, the earliest phase(s) of the FDMP 
shall be implemented. (DT-5) 
Grazing, Cattle
Within Year 1 
Implementation Milestone
: Within one year of the record of decision, the BLM shall modify 
boundaries as necessary relative to cattle allotments.   
Within Year 1 
Implementation Milestone
: The grazing strategy shall be developed within a year of the record 
of decision.  The strategy shall be a written plan detailing the area of removal, natural cattle 
movements, existing and potential improvements, and other constraints of cattle management. 
(LG-17) 
C# HTML5 Viewer: Deployment on AzureCloudService
RasterEdge.XDoc.PDF.dll. RasterEdge.XDoc.PDF.HTML5Editor.dll. Or you can select x86 if you use x86 dlls. (The application cannot to work without this node.).
select text in pdf file; pdf text searchable
C# HTML5 Viewer: Deployment on ASP.NET MVC
RasterEdge.XDoc.PDF.HTML5Editor.dll. When you select x64 and directly run the application, you may get following error. (The application cannot to work without
convert a scanned pdf to searchable text; how to select text in a pdf
Appendices 
Within Year 1 
Implementation Milestone
:
Health Assessments shall be completed within one year of the record 
of decision for the Cronese Lake, Harper Lake, and Ord Mountain allotments. (LG-18)  
Within Year 2
Implementation Milestone
: The grazing strategy shall be implemented within two years of the 
record of decision. (LG-17)   
Within Year 2 
Implementation Milestone
: Health Assessments shall be completed within two years of the 
record of decision for the following cattle allotments: Cady Mountain, Hansen Common, Lacey-
Cactus 
McCloud, Olancha, Rattlesnake Canyon, Rudnick Common, Tunawee Common, and 
Walker Pass. (LG-9)  
Within Year 2 
Implementation Milestone
: Within two years of the record of decision, range fences shall be 
installed in two places to exclude cattle from high concentration tortoise areas found adjacent to 
the Ord Mountain Allotment: (a) along the southern boundary of the allotment, west of the 
Cinnamon Hills, in northern Lucerne Valley; and (b) along the eastern boundary of the 
allotment, in the vicinity of Box Canyon.  (No #) 
Within Year 3 
Implementation Milestone
: Within three years of the record of decision (assuming that the 
grazing strategy given in LG-17 has been implemented), the Implementation Team shall work 
with the BLM to determine if studies are needed to assess cattle impacts and determine any 
adaptive management prescriptions that may be required.  (No #) 
Additionally, new management prescriptions would require modified grazing practices in the 
Ord Mountain, Harper Lake, and Cronese Lakes allotments.  These include the exclusion of 
cattle from specific areas when dry ephemeral forage is below a threshold of 230 pounds/acre.  
This practice would require rest of certain pastures under these conditions, and would 
concurrently result in herding cattle onto other portions of the allotment. (LG-13) 
Another proposal is to strategically place waters so that cattle are concentrated in areas where the 
fewest tortoise-cattle impacts will occur.  The effects of these and other management practices 
must be monitored to determine if the desired effects (i.e., decreased tortoise mortality and 
decreased habitat degradation) are being achieved. (No #) 
Within Year 3 
Implementation Milestone
: All existing cattle guards in desert tortoise habitat shall be modified 
within three years of the record of decision to prevent entrapment of desert tortoises.  New cattle 
guards shall be designed and installed to prevent entrapment of desert tortoises. (LG-7)   
Within Year 3 
Implementation Milestone
: For cattle allotments outside desert tortoise habitat, DWMAs, and 
C# PDF: PDF Document Viewer & Reader SDK for Windows Forms
Choose Items", and browse to locate and select "RasterEdge.Imaging open a file dialog and load your PDF document in will be a pop-up window "cannot open your
how to make a pdf document text searchable; search pdf for text in multiple files
C# Image: How to Deploy .NET Imaging SDK in Visual C# Applications
RasterEdge.Imaging.MSWordDocx.dll; RasterEdge.Imaging.PDF.dll; in C# Application. Q: Error: Cannot find RasterEdge Right click on projects, and select properties.
pdf find text; search pdf files for text
Appendices 
the Mohave Ground Squirrel Conservation Area (Lacey-Cactus 
McCloud, Olancha, Round 
Mountain, and Whitewater allotments), Health Assessments shall be completed within three 
years of the record of decision. (LG-2) 
Within Year 3 ½  
Implementation Milestone
: Within six months [3 ½ years] after the completion of a Health 
Assessment for a specific area (i.e., grazing allotment, watershed, etc.), the BLM shall use the 
information to make a determination and evaluation, which shall serve as baseline information to 
develop corrective management strategies. Where Health Assessments show that standards and 
guidelines are not being achieved, new measures shall be identified to achieve standards and 
conform with guidelines.  The need for specific Allotment Management Plans to be modified or, 
where none exists, newly drafted, shall be considered. (LG-3)   
Within Year 10 
Implementation Milestone
: Grazing will be discontinued on the Whitewater Canyon allotment, 
pending completion of a study within the next 10 years that assesses livestock grazing 
compatibility with conservation of the desert tortoise, arroyo toad, riparian values, and with use 
of, and access to, intermingled private lands. Following study completion, conduct National 
Environmental Policy Act analysis of management alternatives intended to conserve and provide 
for these resources and values consistent with the study, and subsequently issue a grazing 
decision that implements compatible management provisions. (No #)   
Grazing, Sheep
Within Year 1 
Implementation Milestone
: Within one year of the record of decision, the BLM shall modify 
boundaries as necessary relative to sheep allotments.  (No #) 
In the following allotments, boundaries shall be modified so that areas within DWMAs shall no 
longer be available for sheep grazing: Cantil Common, Lava Mountains, Monolith Cantil, 
Shadow Mountains, and Stoddard Mountain (east of Highway 247 and west of National Trails 
Highway). (LG-23)  
Within Year 1 
Implementation Milestone
: Within one year of the record of decision, the BLM shall work with 
affected wool growers to avoid impacts to the Mohave Monkeyflower Conservation Area. (LG-
24) 
Sheep grazing shall be prohibited from those portions of the Stoddard Mountain Allotment that 
occur within the Mohave Monkeyflower Conservation Area. The BLM shall work with the 
lessee to clearly identify monkeyflower habitat that shall be avoided. (LG-24, 25) 
Within Year 2 
Implementation Milestone
: Following the record of decision, the lessees shall be given two years 
notification pursuant to 43 CFR 4110.4-2(b) before the actions in section 2.2.19.6 of the Draft 
are implemented.  (No #) 
GIF to PNG Converter | Convert GIF to PNG, Convert PNG to GIF
Imaging SDK; Save the converted list in memory if you cannot convert at Select "Convert to PNG"; Select "Start" to start conversion procedure; Select "Save" to
pdf find highlighted text; how to select text on pdf
C# PowerPoint: Document Viewer Creating in Windows Forms Project
You can select a PowerPoint file to be loaded into the WinViewer control. is not supported by WinViewer control, there will prompt a window "cannot open your
pdf searchable text converter; how to make pdf text searchable
Appendices 
Within Year 3 
Implementation Milestone
: Within three years of the record of decision, the Implementation 
Team shall work with the BLM to determine if studies are needed to assess the impacts of sheep 
and determine any adaptive management prescriptions that may be required.  (No #) 
The Plan proposes to remove sheep grazing from all DWMAs, which would affect areas south of 
Shadow Mountain Road in the southern portions of the Fremont-Kramer DWMA.  Areas north 
of Shadow Mountain Road have not been grazed since 1991.  The removal of sheep from this 
area should be followed by studies to determine the efficacy of this measure. (LG-23) 
There are also opportunities to study the effects of sheep removal on lands north of Kramer 
Junction, where sheep continue to graze west of Highway 395 but were removed in 1991 east of 
Highway 395. (No #) 
Guzzlers
Within Year 3 
Implementation Milestone
: Within three years of the record of decision, the Implementation 
Team, with input from the CDFG, shall institute a study to determine the impacts of guzzlers on 
tortoises (if any) inside DWMAs.  The results of the study shall be used by the CDFG to 
implement appropriate actions.  (DT-41) 
Law Enforcement
Within Year 1 
Implementation Milestone
: Within one year of the record of decision, the Implementation Team 
shall initiate coordination meetings with BLM and other applicable law enforcement agencies to 
discuss law enforcement needs relative to plan implementation.  (No #) 
Additional law enforcement (ranger patrols) and educational outreach (recreation technicians) 
shall be used in concert with fencing and signs to inform the public of appropriate and 
inappropriate activities in conservation areas. (E-7) 
A minimum of eight (8) Law Enforcement Rangers and eight (8) maintenance workers shall be 
assigned to the DWMAs. (DT-28) 
Law Enforcement Rangers should work closely with the Implementation Team to facilitate Plan 
implementation, enforcement, and adaptive management. (DT-8) 
It is important that a feedback loop exist between law enforcement and the Implementation Team 
to identify problem areas, and in the spirit of adaptive management, to identify issue-specific 
solutions. (DT-28) 
It is important that anyone designing and implementing an education program work with law 
enforcement personnel (including BLM, county animal control, USFWS enforcement agents and 
CDFG rangers) to identify problems and develop solutions. (E-4) 
C# Image: Create C#.NET Windows Document Image Viewer | Online
DeleteAnnotation: Delete all selected text or graphical annotations. You can select a file to be loaded into the there will prompt a window "cannot open your
search text in multiple pdf; can't select text in pdf file
C# Image: How to Use C# Code to Capture Document from Scanning
installed on the client as browsers cannot interface directly a multi-page document (including PDF, TIFF, Word Select Fill from the Dock property located in
make pdf text searchable; select text pdf file
Appendices 
Signing
Within Year 1 
Implementation Milestone
: Within one year of the record of decision, the BLM shall work with 
the Implementation Team to schedule signing of DWMA boundaries and open areas. (E-7) 
DWMA boundaries should be signed or otherwise designated to identify boundaries and 
facilitate enforcement. An appropriate number of signs (to be determined) should be strategically 
placed between the two OHV open areas (Stoddard Valley and Johnson Valley) and the adjacent, 
Ord-Rodman DWMA. A quick field check should determine if boundary is adequately signed. 
(E-7) 
Proper signing on the ground is essential. (E-7)  
NEW MEASURES TO BE IMPLEMENTED: IMPLEMENTATION TEAM 
Core Components
Within Year 1   
Implementation Milestone
: Within one year of the record of decision, Core Components shall be 
designed and implemented by the Implementation Team.  (No #) 
The list of Authorized Biologists and Environmental Monitors maintained by the Implementation 
Team should be available to the County, City, Filming Commissions, and others to facilitate this 
requirement. (DT-14) 
The Implementation Team shall prepare a standard data sheet to record how many, if any, 
tortoises are moved from harm’s way.  The Implementation Team should use these data to 
determine the actual harassment and mortality take of tortoises authorized by the Plan.  The 
Implementation Team will also reassess these data annually, and modify Survey and No Survey 
Areas accordingly. (M-1) 
A hotline number will be provided by the local jurisdiction so that the Implementation Team can 
be contacted if a tortoise is found on the site at the time of ground disturbance. (E-10) 
A monitoring strategy will be designed and implemented to ensure that the management program 
for species is accomplishing its objectives. (M-1, 2)  
The Implementation Team is tasked with producing a standard data sheet and developing a 
tracking system to determine how many tortoises are accidentally killed or incidentally harassed 
as a result of Plan implementation.  It is expected that an annual review of this information will 
enable the Implementation Team, in conjunction with participating jurisdictions, to modify these 
boundary lines as needed. (M-2) 
C# Word: How to Create C# Word Windows Viewer with .NET DLLs
and browse to find and select RasterEdge.XDoc control, there will prompt a window "cannot open your powerful & profession imaging controls, PDF document, tiff
pdf text select tool; how to make a pdf file text searchable
C# Excel: View Excel File in Window Document Viewer Control
Items", and browse to find & select WinViewer DLL; there will prompt a window "cannot open your powerful & profession imaging controls, PDF document, image
how to search a pdf document for text; how to select text in pdf reader
Appendices 
Education
Within Year 1 
Implementation Milestone
: Within one year of incidental take authorization, the Implementation 
Team shall identify the Education Contractor. (E-1) 
A coordinator of educational programs should be identified.  The “education coordinator” should 
work closely with the Implementation Team and/or appropriate regulatory agencies to approve 
the final education program, judge its efficacy, and ensure appropriate implementation. (E-1)  
Within Year 1 
Implementation Milestone
: Upon selection, the education contractor shall meet with the 
Implementation Team to begin to design the education program. Within one year of incidental 
take authorization, a “substantially complete” outline of the education program shall be 
submitted by the contractor to the Implementation Team.  (No #) 
Distribute information and education materials (E-5, 6): 
through schools, museums, private contractors and organizations 
at recreation vehicle shows, off highway vehicle events (e.g., dual sport), and dealer 
associations (Harley-Davidson, Honda, Suzuki, etc.) 
at convenience stores and other walk-in commercial interests   
consider using restaurant  
place settings and napkins as part of public outreach 
through existing portals, such as Friends of El Mirage and Friends of Jawbone 
at the Planning Departments of each participating jurisdiction  
Consider targeting users through green-sticker money, by distributing materials at the time the 
sticker is purchased through Division of Motor Vehicles. (No #) 
The first effort of the education coordinator should be to determine environmental education 
programs that already exist, and to determine gaps in the program.  The coordinator should 
produce and implement the program to, in part, fill in these gaps.  The education coordinator 
should take into consideration the experiences of successful desert education programs, such as 
the Sand Canyon Environmental Education Program, and the Hands Off Pardner program. (E-2) 
The education coordinator should work with non-government organizations with an interest in 
the western Mojave Desert to better reach group members.  The coordinator should work with 
off-highway vehicle groups to help fund existing programs and create new ones as needed to 
increase sensitivity to desert ecology. (E-3) 
In drawing up a single, programmatic education program to be given to construction workers, the 
coordinator should review files maintained by the USFWS and CDFG to see the range of 
education materials that have been used since the listing of the tortoise, for example.  Between 
1990 and 1995, for example, such an approach resulted in rescuing 1,455 tortoises out of harm’s 
way during construction of 171 federally-authorized projects in tortoise-occupied habitats 
(LaRue and Dougherty 1997). (E-4) 
Appendices 
Develop displays, programs, and materials that can be provided to school districts in the West 
Mojave planning area. Fund and/or cooperate with existing programs (San Bernardino County 
ecological study kits, etc.) to provide for enhanced outreach to schools in desert communities. 
(E-5) 
Schools should be targeted at the district level.  Although schools in the West Mojave area 
should be targeted first, it is important to reach the larger area, including the Inland Empire and 
LA County school districts. (E-5) 
Provide support to the efforts of museums, zoos, and other public institutions to develop 
pertinent desert tortoise exhibits, including (E-6): 
The San Bernardino County museum’s program to develop a desert tortoise exhibit. (E-6) 
The Mojave Narrows Regional Park’s development of an outdoor interpretive program involving 
a live-tortoise exhibit. (E-6) 
Ongoing environmental education at the Lewis Center, other programs supported by Edwards 
Air Force Base, the BLM’s community outreach program, etc. (E-6) 
The education program should include the preparation, distribution and/or installation of signs, 
interpretive kiosks, displays, maps, videos, education packets and brochures. (E-7) 
Design and erect a new sign at the Desert Tortoise Natural Area; include in the sign appropriate 
behavior messages and offer an “800" telephone number for information on tortoise adoption. 
(E-7) 
Place information kiosks in pertinent parts of the desert. (E-7) 
Work with Caltrans to design and install separate, free-standing, interpretive kiosks with desert 
tortoise protection information at highway rest areas. (E-7) 
Target off highway vehicle use areas, such as El Mirage and Jawbone; distribute materials 
through volunteer groups associated with those areas. (E-7) 
Portable displays should be developed and produced, including a portable desert tortoise exhibit, 
for use at county fairs, shows, agency offices, shopping malls, museums, and the BLM’s 
California Desert Information Center in Barstow.  User-friendly maps should be prepared which 
show approved routes of travel.  Work with university, media and corporate sponsor(s) to 
develop a quality video on desert tortoises for release to network, local, and cable television 
stations.  Develop educational packets for use in classrooms.   Produce a brochure to be 
distributed by jurisdictions that outlines the farmer’s responsibilities under the endangered 
species act when developing habitat for target species.  Produce a brochure to be distributed by 
jurisdictions describing the burrowing owl and its habitat features in urban areas. (E-7) 
Appendices 
Fencing: Highways
Within Year 1 
Implementation Milestone
: Within one year of incidental take authorization, the Implementation 
Team shall convene a meeting with pertinent jurisdictions to discuss the intent of highway 
fencing, coordination, priorities, and monitoring needs; eventual culvert placement shall also be 
discussed.  (No #) 
Intent 
Proponents wishing to construct new roads or railroads are encouraged to locate them outside of 
DWMAs.  Proponents should implement designs and maintenance procedures that are consistent 
with the existing terms and conditions identified in various biological opinions for roads; 
locations of such roads should consider reserve design relative to the DWMAs and other factors. 
(DT-6) 
Reduce the availability of carcasses of road-killed animals along highways in tortoise habitat. As 
some ravens derive most of their food from road kills, erect barrier fences (1/2 to 1/4 inch mesh 
hardware cloth; Boarman and Sazaki 1996) along roads and highways specified in the fencing 
table to prevent animals from getting killed on roads.  Recommendations may be modified as 
more information and evaluation becomes available. (H3) 
Some of the desired effects of fencing highways that require monitoring include: (a) reduction of 
tortoise mortality; (b) tortoise recolonization of unoccupied habitats immediately adjacent to the 
highways or interstates; (c) reduction of other vertebrate mortality and its effects on raven 
predation, scavenging, and nesting within a mile of the fenced highway; (d) tortoise use of 
culverts to offset the fragmentation of the fenced highway; and (e) reduction of human impacts 
associated with the highway (such as decreased poaching, pet collection and dumping). (No #) 
Coordination 
Placement of fences along paved roadways shall be coordinated among the Implementation 
Team, the California Department of Transportation, the BLM, county road departments and 
others to ensure that access is provided to those routes identified as “open” that intersect with 
roads to be fenced. (DT-18) 
Immediate fencing is preferable, and will have demonstrable results.  The Implementation Team 
will coordinate with the California Department of Transportation and others to fence identified 
easements as soon as possible.  If an opportunity exists to fence a road but culverts cannot be 
installed at the time of fencing, the fencing should proceed because reducing mortality of desert 
tortoises is a more immediate need than promoting genetic interchange.  Culverts would be 
constructed at the time of widening. (DT-21) 
Priorities 
Unless new information reveals a better order of priority, the following roads, which are all 
bounded by proposed DWMAs, will be fenced on both sides in the following order: (i) Highway 
395 between Kramer Junction and Shadow Mountain Road; (ii) Highway 395 between Kramer 
Appendices 
Junction and 20 Mule Team Road; and (iii) the remaining portions of Highway 58 between 
Kramer Junction and Hinkley. (DT-18) 
Monitoring 
The Implementation Team, working with the California Department of Transportation, the BLM, 
county road departments and others shall ensure that fences and culverts are appropriately 
monitored, and that fence integrity and unobstructed culverts are maintained throughout the life 
of this Plan. (DT-21) 
Additionally, the fences must be monitored to cure breaches and ensure fence integrity. (No #) 
Culvert Placement 
Within DWMAs, when roads are fenced to preclude entry by desert tortoises, culverts of 
appropriate design and spacing to allow desert tortoises to pass under the road shall be installed 
to avoid habitat fragmentation and to allow continued gene transfer from one side of the road to 
the other. (DT-21) 
It is important that the USFWS and other entities (i.e., new Recovery Team members) discuss 
the closure of culverts as a mechanism to prevent spread of disease.  The Draft concluded that 
the pattern of older and newer die-off regions might suggest spread of disease from the northwest 
to the south.  Newer die-off regions found in two places south of Highway 58 could be an 
indicator that culverts facilitated spread of disease.  These hypotheses merit consideration by 
experts.   
Feral Dog Management Plan
Within Year 2 
Implementation Milestone
: Within two years of incidental take authorization, the 
Implementation Team, BLM, county animal control, and other applicable entities shall develop a 
Feral Dog Management Plan (FDMP). (DT-5)   
Within Year 3 
Implementation Milestone
: Within three years of the record of decision, if feral dogs continue to 
be a significant threat to tortoises and other covered species, the earliest phase(s) of the FDMP 
shall be implemented. (DT-5) 
Headstarting
Within Year 1 
Implementation Milestone
: Within one year of incidental take authorization, the Implementation 
Team shall meet with BLM, pertinent experts in headstarting, and others to formulate a strategy 
for implementing headstarting.  (No #) 
Implement a headstarting program in areas where tortoises have apparently been extirpated or 
numbers significantly reduced.  These could include but are not limited to areas west and south 
of Fremont Peak, Fremont Valley, and the Desert Tortoise Research Natural Area. (DT-26) 