THELONDONBOROUGHOFCROYDON(WHITGIFTCENTREANDSURROUNDINGLANDBOUNDED
BYANDINCLUDINGPARTSOFPOPLARWALK,WELLESLEYROAD,GEORGESTREETANDNORTH
END)COMPULSORYPURCHASEORDER2014
APPENDICES
OF
PeterJStone BSc,BArch,RIBA
for
MARKSANDSPENCERSCOTTISHLIMITEDPARTNERSHIPANDMARKSANDSPENCERP.L.C.
Objectionnumber
OBJ/062
Dated
January2015
1
How to add jpg to pdf file - insert images into PDF in C#.net, ASP.NET, MVC, Ajax, WinForms, WPF
Sample C# code to add image, picture, logo or digital photo into PDF document page using PDF page editor control
add a picture to a pdf; how to add image to pdf
How to add jpg to pdf file - VB.NET PDF insert image library: insert images into PDF in vb.net, ASP.NET, MVC, Ajax, WinForms, WPF
Guide VB.NET Programmers How to Add Images in PDF Document
add jpg to pdf acrobat; how to add an image to a pdf file
2278/M37.1061/LIVE:90638842.1/JUAM
2
IndexofAppendices
Appendix
Document
PageNumber
r
1
Chronologicalrecordofcommunicationswith
CLP
4-11
2
Zone Z2, , temporary y relocation’ drawing no.
CP-WDE-Z2-00-DR-A-03007rev.P00,dated
02.04.13
13
3
M&S Relocation Strategy y – – Relocation
Opportunities, Croydon n Centrale, , dated
27.06.2014
15-28
4
Relocationplansdated2
nd
October2014
30-32
5
M&S Relocation, Zone Z2 Level 60, First
Floor Level Area 2’, drawing no. . CP-WDE-
Z2-60-DR-A-03002rev.P02,dated10.11.14
34
6
Relocationplansdated12
th
November2014
36-40
7
Relocations plans dated 27th h November
2014
42-45
8
Drawing no. . CP-WDE-Z2-60-DR-A-03005
P00,dated03.12.14
47-50
2
VB.NET PDF Convert to Jpeg SDK: Convert PDF to JPEG images in vb.
Add necessary references page As PDFPage = doc.GetPage(0) ' Convert the first PDF page to page.ConvertToImage(ImageType.JPEG, Program.RootPath + "\\Output.jpg").
add an image to a pdf in preview; how to add a picture to a pdf file
C# PDF Convert to Jpeg SDK: Convert PDF to JPEG images in C#.net
example, this C#.NET PDF to JPEG converter library will name the converted JPEG image file Output.jpg. Convert PDF to JPEG Using C#.NET. Add necessary references
add image to pdf file; add image pdf document
2278/M37.1061/LIVE:90638842.1/JUAM
3
Appendix1
3
C# Image Convert: How to Convert Adobe PDF to Jpeg, Png, Bmp, &
C# DLLs for PDF Conversion to Images. Add necessary references to your C# project: This demo code convert PDF file all pages to jpg images.
add jpg signature to pdf; adding jpg to pdf
C# Image Convert: How to Convert Dicom Image File to Raster Images
Add necessary references to your C# project RasterEdge.XDoc.PDF.dll. inputFilePath = @"C:\input.dcm"; String outputFilePath = @"C:\output.jpg"; // Convert dicom
how to add an image to a pdf in acrobat; add a picture to a pdf document
19th December 2014
Chronological Record of Communication with the Croydon Partnership ("CLP")
13th August 2013
e-mail from Helen Nash to Osbornes attaching .dwg format drawings of the existing Store, confirming M&S 
would be issuing to Westfied (S Yewman) later that day.
16th September 2013
e-mail from M&S to Osbornes advising that Westfield (John Morgan) would be contacting Osbornes to arrange 
a meeting to brief the new development.
17th September 2013
e-mail from Westfield (John Morgan) to Osbornes arranging a briefing session to go through Westfield’s 
proposed scheme such that Westfield could then work up a long term proposal for the existing Store and a 
plan for how this can then be delivered whilst maintaining trade.
19th September 2013
e-mail from Osbornes (M&S's external project manager) to M&S team, advising that,
'Westfield and Hammerson have entered into a JV Partnership for the redevelopment of the Whitgift site in 
Croydon town centre. The development backs onto the existing M&S Store, and there will be consequential 
works to M&S both temporary, to facilitate the build and in the permanent, once the Centre is complete.
Westfield’s outline programme is to Start on Site with the redevelopment in early-2015, with Completion and 
Launch being Autumn 2018.
M&S and Westfield are undertaking to agree HoTs prior to Christmas, which would then be presented to 
Property Board in January 2014 (date to be confirmed).
I attach a Croydon Offline Study 1 – M&S, prepared by Leonard Design Architects on behalf of the JV for further 
information. 
The scheme proposals include an extension to the M&S Store at Ground Floor only to square off the frontage 
onto the new mall at this Level. The Upper Floor Levels remain as existing in footprint. The Offline Study 
includes a desktop exercise for expanding M&S’s sales floor at Second Floor Level. Having discussed this with 
both Helen and Rob Morray, I am advised M&S will not want to do this. However, opening up an entrance onto 
the newly created mall will be required. M&S will also be exploring whether in the final scheme they will want 
to relocate the Food Hall from First Floor to Ground Floor.
John Morgan of Westfield would like to arrange a meeting on-site to run through the scheme proposals and 
review constraints and operational issues which we may identify during the visit. Due to the potential 
complexity and pace with which we will be moving this forward to agree HoTs prior to Christmas, I would like 
the entire Team to attend this first meeting'.
3rd October 2013
Meeting at Croydon with Westfield to agree actions for all parties to progress in the context of the 'planning 
scheme' - programme for Feasibility Study outputs to be achieved over the next month discussed - Westfield to 
underwrite and reimburse M&S their costs in connection with the feasibility exercise.
4th October 2013
e-mail from ttg to Westfield (N. Loveridge) issuing CAD information (as avaialable) for the existing M&S store 
and requesting CAD plans of the 'planning scheme' as tabled on 3rd October for inclusion in 'context' plans for 
review the the M&S Store Planning Team.
4th October 2013
e-mail from Westfield (N. Loveridge) to ttg acknowledging receipt of information and requesting any further 
structural information, as available for the M&S unit.
4th October 2013
e-mail from Westfield (N. Loveridge) to ttg issuing a link to the 'planning scheme GA Plans and Sections in DWG 
and PDF' format.
4th October 2013
e-mail from ttg to Westfield (N. Loveridge) advising that M&S's Consultant Structural Engineers (Melliss LLP) 
had confirmed that no electronic records of the structural information appeared to exist in the current M&S 
records/archives so they would go back through any previous Engineers who have had involvement on this 
store to see if there was anything that could be sourced.
8th October 2013
e-mail from ttg to Westfield (N. Loveridge) advising that having reviewed the Basement level plan from the 
‘Planning’ set it was not entirely clear what was intended for the M&S delivery vehicles, noting the intention to 
reverse the vehicle flow through the basement service road, issuing a sketch to indicate an arrangement that 
could work for M&S taking account of the increased store size and noting that this could be 
reviewed/discussed at the first ‘Review Meeting/Design Workshop’.
4
C# Create PDF from images Library to convert Jpeg, png images to
images.Add(new Bitmap(Program.RootPath + "\\" 1.jpg")); images.Add(new Bitmap(Program.RootPath + "\\" 1.png")); / Build a PDF document with
how to add picture to pdf; add photo to pdf preview
C# WPF PDF Viewer SDK to convert and export PDF document to other
Highlight Text. Add Text. Add Text Box. Drawing Markups. Add Stamp Annotation. image file formats with high quality, support converting PDF to PNG, JPG, BMP and
add photo to pdf form; how to add a jpeg to a pdf file
8th October 2013
e-mail from ttg to Westfield (N. Loveridge) advising comments regarding the existing NCP which the planning 
scheme proposed to retain and redfurbish. It was noted that following a further visit on 8th October, that this 
would be better demolished and rebuilt due to the standard of the existing and that this then provided the 
option for the car park access (entrance/exit) to be relocated from Poplar Walk to Wellesley Road, on which 
basis Westfield couldconsider demolishing the existing car park access ramp to form the new ’boulevard’ walk 
into the centre instead of demolishing the final bay at the eastern side of the existing M&S store, as indicated 
by the planning scheme.
8th October 2013
e-mail from ttg to Westfield (N. Loveridge) requesting a drawing illustrating the strategic traffic flow patterns 
that are anticipated if they were to implement the ‘Planning ‘ scheme, noting that it was likely that their 
Highways Consultant (WSP?) would have produced something. This would assist the M&S team in appreciating 
the alterations in traffic patterns and access/egress points for the overall scheme and also the anticipated 
approach routes around central Croydon if public access to the car park was still anticipated from Poplar Walk.
8th October 2013
e-mail from ttg to Westfield (J. Morgan) asking whether they were aware whether JLP intend to include a 
Waitrose within their new store and if so what Level they anticipate locating it on in order to assist ttg in 
reviewing the layout and ‘department’ locations of the M&S store for the ‘Optimum’ scheme.
9th October 2013
e-mail from ttg to M&S confirming that if a new store were being evaluated, a GIA of 170,000-175,000 sqft 
should be requested in order to deliver 120,000 sqft net sales floor space. 
9th October 2013
e-mail from ttg to Westfield (N. Loveridge) requesting technical details for the Westfield Revit model of the 
scheme to check compatibility with ttg's current software.
9th October 2013
e-mail from Westfield (N. Loveridge) to ttg advising that in response to the query re. the Basement level 
servicing, that at this stage, particularly at the lower ground, they would 'be minded not to pay too much 
attention to the illustrative scheme' and that they 'would like to first and foremost land a scheme that works 
for M&S', noting that obviously they would 'have to be mindful of the redline boundary, but in layout terms 
they could pretty much treat this as a blank canvas in this area'. They confirmed that they were happy to 
discuss all options at the next review and could arrange for tracking once the preferred solution was agreed.
9th October 2013
e-mail from Westfield (N. Loveridge) to ttg in response to the comments re. the NCP car park, that at that stage 
their preference was to keep the car park entrance off Poplar Walk and exit onto Wellesley Road as this 
approach allowed the traffic to be calmed on Wellesley Road which was the planners desire. They advised that 
their current traffic modelling was based on this design, but that wasnt to say they couldn’t explore further. 
They confirmed an initial conversation with WSP and that their thoughts were it may not be possible with 
traffic arriving from the North queuing over the Poplar Walk intersection, but they were looking into to it in 
more detail. An offline option they had looked at and should still consider could be to demolish the entire 
existing car park ramp, replace with public realm/entrance, and build the new entrance to the East of the 
Service ramp exit (in the Green Park House land).
9th October 2013
e-mail from Westfield (N. Loveridge) to ttg confirming the details of their Revit model software. 
9th October 2013
e-mail from Westfield (N. Loveridge) to ttg confirming that JLP had not confirmed their intention re. Waitrose.
14th October 2013
e-mail from ttg to Westfield (N. Loveridge) issuing further drawings for the existing M&S store, including 
further information for the Basement and Roof level.
5
C# PDF File Merge Library: Merge, append PDF files in C#.net, ASP.
Combine scanned images to PDF, such as tiff, jpg, png, gif, bmp, etc. Add necessary references: In addition, C# users can append a PDF file to the end of a
add signature image to pdf; add jpg to pdf preview
VB.NET PDF File Merge Library: Merge, append PDF files in vb.net
to combine various scanned images to PDF, such as tiff, jpg, png, gif Add necessary references: In addition, VB.NET users can append a PDF file to the end of a
adding images to pdf files; add image pdf
14th October 2013
Summary Status report of progress issued by ttg to M&S team, as below following the briefing meeting held 
3rd October:
1. Melliss to ascertain if Record Drawings for the structure of the existing store are available.
2. SDS to review likely power requirements for ‘Flagship’ store – 120k net sales and review if existing supply 
capacity is sufficient.
3. SDS to review existing plant equipment at roof level and advise on existing redundancy and likely 
retention/replacement strategies for extended store.
4. Record drawings of all levels have been issued to Westfield to develop the REVIT model.
5. Scheme drawings for the ‘Planning scheme’ have been received from Westfield.
6. Design review undertaken at basement good/reception level and indicative proposal for extended 
basement/vehicle delivery positions issued to Westfield.
7. Further site inspection undertaken of NCP car park and recommendation issued to Westfield that this is 
demolished and re-built to address accessibility issues.
8. Initial Footage appraisal undertaken and discussed with Rob Morray and Matthew Knowles to determine 
practicalities of existing store being re-planned to suit anticipated BU’s.
9. TTG to meet with Store Planning to review initial analysis.
10. Westfield asked to review car-park access/egress positions regarding Welesley Rd/poplar walk.
11. TTG to review Westfield proposal to demolish and relocate existing car park ramp from poplar walk to the 
east of the service road ramp.
12. TTG to prepare high level ‘block layouts’ following review meeting with store Planning.
13. Store Planning to provide TTG with sales estimates to enable review of assumptions on stock and staff 
quarter requirements.
14. M&S/Croydon Partnership to confirm fee agreement re ‘M&S Consultants’.
15. Osborne/Westfield to coordinate design review/workshop dates.
22nd October 2013
Design Review/Workshop meeting at Westfield, Holborn to review progress of scheme proposals.
22nd October 2013
e-mail from ttg to Westfield (N. Loveridge) issuing the existing store Fire Strategy drawings prepared by Styles 
& Wood in 2006 and advising floor space factor for M&S's existing Basement stockroom.
22nd October 2013
e-mail from Westfield (N. Loveridge) to ttg confirming that they had received the Fire Strategy drawings and 
would forward to JGA (Jeremy Gardner Associate - Fire Consultants) for review.
23rd October 2013
e-mail from Westfield (N. Loveridge) to ttg issuing a link to their Revit model.
24th October 2013
e-mail from Westfield (N. Loveridge) to ttg issuing their predicted footfall data for Croydon, as requested on 
22nd October 2013.
24th October 2013
e-mail from ttg to Westfield (N. Loveridge) noting the presumption that at this stage the footfall penetration 
into the actual scheme ie the mall/arcade access points had not yet been developed, but if so, even as a 
preliminary draft, requesting it be issued. Query also raised regarding the 2017 Modal Split for the tram 
arrivals.
24th October 2013
e-mail from Westfield (N. Loveridge) to ttg confirming that the Footfall data had not been developed in any 
further detail and confirming our understanding of the Tram system was correct.
5th November 2013
Design Review/Workshop meeting at Westfield, Holborn to review progress of scheme proposals.
6th November 2013
e-mail from ttg to M&S team following meeting with Westfield/Hammerson on 5th November, issuing a 
schematic overview of the extent of alterations being considered for the M&S store to create the Optimum 
flagship proposal, noting that Westfield seemed keen to try and double stack plant on the re-built corner plot 
where North End and Poplar Walk meet, and asking whether this was  viable on the basis that the Wine Bar 
would vacate and all new structure could be provided to that area. Also noted that ttg were working on the 
preliminary retail block plans and would be reviewing these with (M&S) store planning.
12th November 2013
M&S review meeting to assess potential Block Plans and internal layouts to store.
13th November 2013
e-mail from ttg to Westfield (N. Loveridge) requesting CAD plans for the existing Whitgift Centre to enable 
some background information for the M&S Food Director to review the impact of relocating the food sales 
area from its existing location (at First floor) down to Ground floor level in respect of car park proximities, 
entrances etc.
13th November 2013
e-mail from Westfield (N. Loveridge) to ttg, issuing CAD files of the current Whitgift Centre.
6
6th March 2014
Meeting between M&S and Westfield - Westfield presented a scheme for the rebuild of the M&S store, as the 
document 'Croydon - Presentation to M&S 2014/03/05'. M&S requested that a follow up meeting be arranged 
by Westfield with ttg architects and Osbornes to start to 'workshop any operational challenges'.
7th March 2014
e-mail from ttg to M&S advising that based on the scale of the redevelopment required to build the suggested 
new store, it would be unlikely and improbable that M&S could contemplate trading through the course of the 
construction works and that an interim relocation would need to be considered in parallel with the option to 
rebuild.
7th March 2014
e-mail from M&S to ttg confirming that they had requested options from Westfield for temporary units of 
15,000 sqft for Food and 40,000 sqft for GM, either together or separately.
25th March 2014
Meeting with Westfield to review the proposal for the new store. M&S requested Westfield provide 
schematics of what the existing store would look like throughout the development if they chose to not proceed 
with the redevelopment and decided that retaining and refurbishing/extending the existing building was the 
preferred option. 
31st March 2014
e-mail from Osbornes to Westfield (S. Wood) advising of an internal M&S review on 8th April 2014 and 
requesting further clarification as to the available options for temporarily relocating in the town centre, 
together with advice regarding the impact of the Works on the existing Store’s sales floors (approximate %-age 
of sales floor lost at any one time) in the event that a new build Store is unfeasible and M&S continue to trade 
from their existing Store throughout the redevelopment.
7th April 2014
e-mail from ttg to M&S confirming that no information had been received from Westfield on the impact on the 
existing store if M&S chose to remain ‘on-site’ and opt for the extension/refurbishment of the current store 
whilst the Whitgift is demolished and re-built. 
15th April 2014
CPO set.
30th April 2014
Meeting at King & Wood Mallesons LLP to review CPO - M&S noted that Westfield had advised that they 
believed they could provide one unit with a GIA of c 15,000 sq.ft for a Simply Food and a separate unit with a 
25,000 sq.ft for a small GM offer.
6th May 2014
Meeting at King & Wood Mallesons LLP to review CPO.
8th May 2014
e-mail from Westfield (S. Yewman) to M&S issuing a 'draft of the potential relocation options', ‘Zone Z2, 
temporary relocation’ drawing no. CP-WDE-Z2-00-DR-A-03007 rev. P00, dated 02.04.13 (sic).
12th May 2014
e-mail from Westfield (S. Yewman) to M&S asking whether M&S had 'any further thoughts' on relocation 
options, noting that they had not 'been fully resolved yet'. The e-mail also contained indicative 'milestone 
dates' as below,
- Make/Serve CPO notice                         April 2014
- CPO Inquiry                                               September/November 2014
- Secretary of State confirmation         February/April 2015
- Commence vesting of land                  June/September 2015
- Main demo/build (retail/leisure)     June/September 2015
- JLP shell & core complete                    September/October 2017
- Complete for trading                             September/October 2018
30th July 2014
M&S Property Board approves progression of the new build store option 'in principle' and temporary 
relocation into the Centrale Shopping Centre whilst Westfield redevelop the Whitgift Site. 
4th August 2014
e-mail from Helen Nash to Osbornes confirming M&S met with Steve Yewman of Westfield on 04/08/14 to 
review both the temporary Store options and new build Store; asking that Osbornes contact Westfield to 
arrange access to inspect the proposed temporary Stores in the Centrale Shopping Centre.
5th August 2014
e-mail from Westfield (N. Loveridge) to Osbornes with 'a link to Westfield’s ‘Relocation Opportunities’ 
document (M&S Relocation Strategy – Relocation Opportunities, Croydon Centrale’, dated 27.06.2014) which 
includes the two Options'.
7
19th August 2014
Meeting with the Croydon Partnership at Centrale, Croydon to review potential temporary relocation areas 
being offered.
21st August 2014
e-mail from ttg to Westfield (D. Glanz) requesting CAD plans for each relocation area, or the Revit model, 
following the visit to Centrale.
22nd August 2014
e-mail from Westfield (N. Loveridge) to ttg, issuing CAD files of the M&S relocation options from their Revit 
model.
4th September 2014
Preliminary assessment of the temporary relocation options issued by ttg to M&S.
4th September 2014
M&S internal review of relocation area options.
11th September 2014
e-mail from Helen Nash advising that Westfield were not at this time prepared to offer M&S the Poundworld 
Unit for use as a Simply Food Store.
23rd September 2014
e-mails from Westfield (N. Loveridge) to Osbornes issuing the relocation area 3 (Poundworld) in pdf and dwg 
format.
24th September 2014
e-mail from Westfield (N. Loveridge) to Osbornes issing the relocation area LSU6b (part of area 1) in pdf and 
dwg format.
29th September 2014
M&S internal review (N. Hyslop) of relocation area options and confirmation of preference for Poundworld unit 
for food, with both relocation areas at First floor for GM.
2nd October 2014
e-mail from Helen Nash to ttg  confirming  that Westfield had agreed in principle to progress on the basis 
that 'the temporary locations will be the Poundworld unit (relocation area 3), the two first floor units as 
drawn on latest scheme (relocation areas 1 and 2), a relocation (turning through 180°) of the escalator in the 
mall serving the first floor and signage on to North End'.
6th October 2014
e-mail from Westfield (N. Loveridge) to ttg with a link to the Revit model of the Centrale Centre to enable M&S 
to produce information for an M&S review on 6th October 2014.
14th October 2014
Meeting held with The Croydon Partnership to review the demise to the temporary relocation areas in 
Centrale (including access to Poundworld (relocation area 3 - Food) and their proposals for the new store. 
Agreed actions as Peter Tunwell e-mail of 16th October 2014 to M&S, ie. The Croydon Partnership to provide 
feedback/information within one week of the meeting, ie. by 21st October 2014. 
15th October 2014
e-mail from ttg to Westfield (N. Loveridge) issuing plans to the relocation areas indicating our understanding of 
the demises to be offered following the site visit and meeting of 14th October 2014.
15th October 2014
e-mail from Westfield (N. Loveridge) to ttg with a link to the existing Centrale CAD and pdf files. These were 
qualified as being via Hammerson from Coleman Architects and therefore their accuracy could not be 
guaranteed. It was advised that the Whitgift (new store) CADs had been 'cropped down due to CPO difficulties'. 
Noted that the M&S store was an' early guess as to what may be required' and that they were 'more than 
happy for M&S's requirements to drive grids sizes, entrance positioning, mall alignments etc. for discussion 
and agreement going forward.' NB: the layouts indicated to the new store were CAD versions of the indicative 
plans contained in the document 'Croydon - Presentation to M&S 2014/03/05'.
16th October 2014
e-mail from ttg to M&S confirming the outcome of the meeting of 14th October and scheduling those actions 
and information to be issued by The Croydon Partnership. 
17th October 2014
e-mail from ttg to Westfield (N. Loveridge) confirming the GIA required at each level by M&S for the new store 
to enable Westfield to develop the layouts, including the potential release of assumed footage at Ground floor 
level, providing additional area for units and commercial benefits to the mall.
17th October 2014
e-mail from ttg to Westfield (N. Loveridge) querying whether they were able to confirm the demise for the 
relocation areas, based on the H&M Lease.
21st October 2014
e-mail from ttg to M&S issuing our presumed demise for the relocation areas, based on the understanding of 
the H&M Lease.
8
22nd October 2014
e-mail from ttg to Westfield (N. Loveridge) querying whether the revised relocation demise drawings were 
available, as advised at the meeting on 14th October 2014.
24th October 2014
e-mail from ttg to Westfield (N. Loveridge) confirming those items which should have been addressed by The 
Croydon Partnership by 21st October 2014, following the meeting on 14th October 2014.
24th October 2014
e-mail from Westfield (S. Yewman) to ttg confirming that Hammerson (B. O'Neill) would be able to confirm the 
last points on the Centrale tenancies (relocation areas) on 27th October 2014. e-mail also suggested that 'in 
regard the  new store it would be good to catch up next week to discuss'.
27th October 2014
e-mail from ttg to Hammerson (B. O'Neill) confirming Wesfield's (S. Yewman) advice of 24th October 2014, 
that Hammerson (B. O'Neill) would be able to confirm the last points on the Centrale tenancies on 27th 
October 2014. e-mail also attached drawings indicating ttg's understanding of the revised relocation areas, 
together with a schedule of Queries & Responses, as produced following the meeting on 14th October 2014.
28th October 2014
Meeting at Centrale (ttg and Hammerson (B. O'Neill)) to review Back of House areas to relocation area 2.
31st October 2014
e-mail from ttg to Hammerson (B. O'Neill) issuing ttg's file note produced following the visit to Centrale on 
28th October 2014.
31st October 2014
Meeting at Hammerson, with Ben O'Neill (Hammerson), David Garaway (Westfield), Nigel Clarke (lead 
manage), Edwin Bergbaum (Waterman, Structural Engineer), Nick Harvey (JGA Fire Engineering Consultants), 
Peter Stone and Mike Lewin (ttg architects) to review demise to relocation units. 
Advised that Waterman were reviewing the structure and available loadings - advised that the area where the 
floor was to be raised to relocation area 2 would only achieve a maximum of 3 Kn/m² load capacity. 
JGA advised that they had had an initial look at the layouts and would prepare a Fire Strategy on receipt of an 
appointment, following which it would take about 8 days to produce.
3rd November 2014
e-mail from ttg to M&S confirming the outcomes from the meeting held on 31st October 2014, ie. potential 
loading restriction etc.
3rd November 2014
e-mail from ttg to M&S advising that M&S's Structural Engineers had confirmed that a load capacity of 3Kn/m² 
is not sufficient for a sales area and advising the footage to relocation area 2 which would not be usable if this 
maximum loading was confirmed.
3rd November 2014
e-mail from ttg to Westfield (S. Yewman) advising those actions due by 21st October not yet complete.
4th November 2014
e-mail from Westfield (S. Yewman) to ttg confirming that he would pick up the actions due by 21st October 
with his team and revert.
5th November 2014
e-mail from Hammerson (B. O'Neill) to ttg issuing Lead Management's notes for the meeting held on 31st 
October 2014.
6th November 2014
e-mail from ttg to Hammerson (B. O'Neill) commenting on the notes issued for the meeting held on 31st 
October 2014.
7th November 2014
e-mail from ttg to M&S issuing plans showing three options for the temporary GM units at First floor based on 
presumed demises, awaited from The Croydon Partnership.
10th November 2014
e-mail from Hammerson (B. O'Neill) to ttg issuing updated copy of plan for relocation area 2 illustrating the 
'worst case' and highlighting risk/opportunity areas. Reference to Waterman marking up available loadings and 
JGA confirming the Fire Strategy.
10th November 2014
e-mail from ttg to Hammerson (B. O'Neill) returning copy of relocation area 2 marked with comments  
regarding clarification of the demise.
12th November 2014
e-mail from Hammerson (B. O'Neill) to ttg issuing updated copies of plans for relocation areas.
9
12th November 2014
e-mail from Westfield (S. Yewman) to ttg confirming that he expected to have a set of resolved options for the 
relocation areas for review w/c 17th November 2014 and requesting further input form M&S on vertical 
circulation and department mix.
12th November 2014
e-mail from ttg to Westfield (S. Yewman) responding to e-mail from Westfield (S. Yewman) to ttg of 12th 
November querying why further information was being requested and advising that the information requested 
by Westfield was not relevant or required to provide the information relating to the new store previously 
agreed to be issued by 21st October. 
13th November 2014
e-mail from Westfield (S. Yewman) to ttg advising that they would advise when ready to discuss (e-mail from 
ttg of 12th November 2014).
13th November 2014
e-mail from ttg to Hammerson (B. O'Neill) querying demise to First floor relocation area 1 surrounded by LSU6c 
as received on 12th November not being as previously agreed.
13th November 2014
e-mail from Hammerson (B. O'Neill) to ttg confirming that ttg's understanding of the demise surrounded by 
LSU6c as ttg e-mail of 13th November was correct. e-mail also enclosed an updated drawing of the 'food court' 
(relocation area 2) indicating the proposed hanger arrangement to suit the infilling of the 3 No. mall voids.
14th November 2014
e-mail from ttg to Hammerson (B. O'Neill) querying demise to First floor relocation area 2 - area omitted to 
rear of H&M. e-mail also confirmed agreement in principle to arrangement of new hangers to suit the infilling 
of the 3 No. mall voids.
14th November 2014
e-mail from ttg to Hammerson (B. O'Neill) advising that 'there appears to be survey information, particularly 
relating to the section and the back of house layout in the existing Poundworld unit', that ttg did not have in 
CAD form and requesting its' issue.
17th November 2014
CAD files for the back of house detail to the Poundworld unit (relocation area 3) issued by Westfield (D. 
Garaway) to ttg.
19th November 2014
Meeting at M&S with Westfield (S. Yewman) - confirmation that they would issue a set of resolved options 
(demises) for the relocation areas together with further proposals for the new store (based on the required 
GIAs advised by ttg on 17th October) by 28th November 2014. Also confirmed that the 4 Kn/m² loading could 
be provided to the area of raised floor to relocation area 2. 
21st November 2014
e-mail from ttg to Westfield (S. Yewman) re-issuing e-mail to Westfield (N.Loveridge) of 17th October 2014, 
confirming the required GIA at each level to the new store, as issued at the meeting on 19th November 2014.
25th November 2014
e-mail from Osbornes (Carl Matthews) to Westfield (S. Yewman) issuing the Shell Specification for the previous 
development at Stratford City, for reference and information and advising that they would produce a 
Specification for the new store using this as a template.
27th November 2014
e-mail from Westfield (S. Yewman) to Osbornes (Carl Matthews) acknowledging receipt of the Specification 
and advising that he expected 'to have the turn on floor areas etc by the end of the week' (28th November) 
and on Tuesday (2nd December) he was 'meeting the Centrale relocation team to understand, Costs and 
deliverability'. He suggested that 'towards the end of next week we should have a sit down to check over the 
plans', ie. w/c 1st December 2014.
27th November 2014
e-mail from Hammerson (B. O'Neill) to ttg attaching pdf files of updated drawings for the three relocation 
units.
28th November 2014
e-mail from ttg to Hammerson (B. O'Neill) requesting that the drawings issued on 27th November 2014 be 
issued in CAD format, including the proposed demise lines.
28th November 2014
e-mail from ttg to Hammerson (B. O'Neill) identifying 13 No. access doorsoff the proposed demise area in the 
latest drawing of Relocation area 2 and requesting clarification as to which were to be maintained and, if so, 
what frequency of access was envisaged?
1st December 2014
e-mail from Hammerson (B. O'Neill) to ttg attaching CAD files  of the drawings issued on 27th November 2014 
and enquiring as to whether ttg were able to issue indicative fit-out plans.